OK <br />PV Panel W 3.00 psf <br />Area of panel 220.00 ft2 <br />Total Roof W 550.46 lbs <br />% increase=(Wadditional)/Wexisting 1.44% <br />The increase in weight as a result of the solar system is less than 10% of the existing structure and therefore no further seismic analysis is required. <br />Limits of Scope of Work and Liability <br />Existing structure is assumed to have been designed and constructed following appropriate codes at time of erection, and assumed to have appropriate permits. The calculations produced are only for the roof framing supporting the proposed <br />PV installation referenced in the stamped planset and were completed according to generally recognized structural analysis standards and procedures, professional engineering and design experience, opinions and judgements. Existing <br />deficiencies which are unknown or were not observable during time of inspection are not included in this scope of work. All PV modules, racking, and mounting equipment shall be designed and installed per manufacturer's approved installation <br />specifications. The Engineer of Record and Engineerinc assume no responsibility for misuse or improper installation. This analysis is not stamped for water leakage. Framing was determined based on information in provided plans and/or <br />photos, along with engineering judgement. Prior to commencement of work, the contractor shall verify the framing sizes, spacings, and spans noted in the stamped plans, calculations, and cert letter (where applicable) and notify the Engineer of <br />Record of any discrepancies prior to starting construction. Contractor shall also verify that there is no damaged framing that was not addressed in stamped plans, calculations, and cert letter (where applicable) and notify the Engineer of Record <br />of any concerns prior to starting construction. Prior to the commencement of work, the contractor shall verify the existing roof and framing conditions. Notify Engineerinc and the engineer of record of any Discrepancies prior to starting <br />construction. Prior to the commencement of work, the contractor shall inspect framing for any damage such as water damage, cracked framing, etc. and notify the E.O.R. if any issues are found.These plans/calculations are stamped for <br />structural code compliance of the roof framing supporting the proposed PV installation reference only. These plans/calculations are not stamped for water leakage. PV modules, racking, and attachment components must follow manufacturer <br />guidelines and requirements. <br />303 N. Glenoaks Blvd Suite #200 Burbank, CA 91502 | (747)333-5991 | new@engineerinc.io <br />1424 N Flower St <br />02/15/23