By: T.S. <br />Date: 12/15/23 <br />Gravity Loads: <br />DEMAND DECREASED BY 11.54% = OK! <br />Lateral Loads: <br />DEMAND INCREASED BY 4.96% < 10% = OK! <br />Anchorage: <br />DEMAND OF 233.LB. < CAPACITY OF 851.2LB. = OK! <br />USE (1) 5/16IN. DIA. LAG SCREW(S) AT 6FT. MAX. O.C. W/ 2.5IN. MIN. PENETRATION <br />Summary: <br />STRUCTURE IS ADEQUATE FOR THE PROPOSED PV ARRA <br />ANCHORS ON EAVES/OVERHANGS ARE OK! <br />Summary <br />12/15/2023 11:51 AM <br />7 of 7 <br />©McPherson Engineering <br />3229 S Park Dr <br />Unit# 21/23/2024