HomeMy WebLinkAbout20 Civic Center Plaza - Soils ReportECEIVED
APR 2 7 1998
City of Santa Ana
LAW Crandall
LAWGIBB Group Member 1
REPORT OF GEOTECHNICAL INVESTIGATION
PROPOSED PLANNING AND
BUILDING AGENCY BUILDING
SANTA ANA BOULEVARD AND ROSS STREET
SANTA ANA, CALIFORNIA
Prepared for:
GRIFFIN REALTY SA, INC.
Santa Ana, California
July 8, 1997
Project 70131-7-0261.0001
I DI I1042-
r-?J 31.rap 42 0 <yz
LAW Crandall
LAWGIBB Group Member A
July 8,1997
Mr. Roger Nello Torriero
Griffin Realty SA, Inc.
6 Hutton Center Drive, Suite 820
Santa Ana, California 92707
Subject:Report of Geotechnical Investigation
Proposed Planning and Building Agency Building
Santa Ana Boulevard and Ross Street
Santa Ana, California
Law/Crandall Project 70131-7-0261.0001
Dear Mr. Torriero:
We are pleased to submit the results of our geotechnical investigation for the proposed Planning
and Building Agency building to be constructed at Santa Ana Boulevard and Ross Street in Santa
Ana, California. This investigation was conducted in general accordance with our proposal dated
May 27,1997, as authorized by you on May 27,1997.
The results of our investigation and design recommendations are presented in this report. Please
note that you or your representative should submit copies of this report to the appropriate
governmental agencies for their review and approval prior to obtaining a building permit.
We are performing a Phase 1 environmental site assessment of the site of the proposed building.
The results of the assessment will be submitted under separate cover.
LAW Engineering and Environmental Services, Inc.
200 Citadel Drive
Los Angeles, CA 90040-1554
213-889-5300 · Fax. 213-721-6700
Grifin Realty SA, Inc. - Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8,1997
It is a pleasure to be of professional service to you on this project. Please call if you have any
questions or require additional information.
Sincerely,
LAW/CRANDALL *:EAAEL H, ,{Di
No. 54974 Exp.6-30-00
Michael W. Han CCe/#ACVLVT
Staff Engineer -1.=M-QMS,0,
< No. 2371 MI No. 2087
Paul R. Schade 1*\ Exp. 9/30/00 fj Jake Kliafraz - '- - * Exp. 9-30-99 *Senior Engineer Principal Engineer TECHN\43-e n g g e o \ 9 7 - p roj \ 7 0 2 61 \0 2 6 1 1 RO 1' B i * I..j Nt£23/
(3 copies submitted)
32
CC:John A. Martin & Associates, Inc.
Attn: Mr. Chuck Whitaker
McLarand, Vasquez & Partners, Inc.
Attn: Mr. Jim Mittendorf
REPORT OF GEOTECHNICAL INVESTIGATION
PROPOSED PLANNING AND BUILDING AGENCY BUILDING
SANTA ANA BOULEVARD AND ROSS STREET
SANTA ANA, CALIFORNIA
Prepared for:
GRIFFIN REALTY SA, INC.
Santa Ana, California
Law/Crandall
Los Angeles, California
July 8, 1997
Project 70131-7-0261.0001
Gri#in Realty SA, Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8.1997
TABLE OF CONTENTS
Eagg
LIST OF FIGURFR It!
SUMMARY iv
1.0 SCOPE 1
2.0 PROJECT DESCRIPTION 2
3.0 SITE CONDITIONS 3
4.0 EXPLORATIONS AND LABORATORY TESTS 3
5.0 SOIL CONDITIONS 4
6.0 RECOMMENDATIONS 4
6.1 FOUNDATIONS 5
6.2 SITE COEFFICIENT AND SEISMIC ZONATION 7
6.3 EXCAVATION AND SLOPER 7
6.4 SHORING 8
6.5 WALLS BELOW GRADE 13
6.6 FLOOR SLAB SUPPORT 14
6.7 PAVING 15
6.8 GRADING 16
6.9 GEOTECHNICAL OBSERVATION 17
7.0 BASIS FOR RECOMMENDATIONS 18
APPENDIX A:EXPLORATIONS AND LABORATORY TESTS
APPENDIX B:SOIL CORROSIVITY STUDY BY M.J. SCHIFF AND ASSOCIATES
It
Gri#in Really SA, Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8, 1997
1
LIST OF FIGURES
1 Site Plan
2 Drilled Pile Capacities
1
1
1
1
1
1
1
1
1
1
lili
Gri#in Realry SA, Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8, 1997
SUMMARY
We have completed our geotechnical investigation of the site of the proposed Planning and
Building Agency building in Santa Ana, California for Griffin Realty SA, Inc. Our subsurface
explorations, engineering analyses, and foundation design recommendations are summarized
below.
We explored the soil conditions by drilling two borings at the site; fill soils, 2 and 3 feet thick,
were found in the two borings. The natural soils consist of sandy silt, clayey silt, silty sand and
sand. To supplement our current geotechnical analyses, we also reviewed our report of foundation
investigation, dated November 7, 1958, for the existing on-site police building which will be
demolished. The geotechnical recommendations in this report were developed in part using
information from our previous investigation.
The existing fill soils are not suitable for support of the proposed building foundations and fioor
slab. The natural soils consist primarily of medium stiffsilt, with minor deposits of dense sand and
silty sand. The upper natural soils become considerably weaker and more compressible when wet.
Water was encountered at depths of 65'h and 67'h feet below the existing grade.
To provide support for the proposed building with minimum settlement, drilled cast-in-place
concrete piling may be used. We understand that the drilled cast-in-place piles for the existing
police building will be left in-place but will not be used for support of the new building. The on-
site soils are suitable for use as compacted fill, and the building floor slab can be supported on
grade.
iv
Gri#in Realry SA, Inc.-Geotechnical Investigation
Uiw/Crandall Project 70131-7-0261.0001
July 8, 1997
1.0 SCOPE
This report provides foundation design information for the proposed Planning and Building
Agency building in Santa Ana, California. The locations of the existing building and our
exploration borings are shown in Figure 1, Site Plan.
We submitted the results of our foundation investigation at the site for the existing police building
in a report dated November 7, 1958 (our Job No. 58338). The locations of our previous
exploration borings are shown in Figure 1. The recommendations presented in this report were
developed in part using geotechnical information from our previous investigation.
This investigation was authorized to determine the static physical characteristics of the soils at the
site of the proposed building, and to provide recommendations for foundation design, floor slab
support, and for grading for the proposed development. We were to evaluate the existing soil and
groundwater conditions at the site, including the corrosion potential of the soils, and develop
recommendations for the following:
• Design of new foundations to be used for support of the proposed building,
including allowable increases for wind or seismic loads, estimated
settlements for the anticipated loadings, and frictional and passive values for
the resistance of lateral forces.
• Subgrade preparation and floor slab support.
• Design of walls below grade and retaining walls.
• Design of shoring.
• Subgrade preparation and design of asphalt and Portland cement concrete
paving.
• Grading, including site preparation, excavation and slopes, the placing of
compacted fill, and quality control measures relating to earthwork.
In addition. corrosion studies were performed by M.J. Schiff and Associates, Inc., Consulting
Corrosion Engineers. The results of the studies are presented in Appendix B.
1
Griffin Realty SA, Inc.-Geotechnical investigation
Law/Crandall Project 70131-7-0261.0001
July 8, 1997
The scope of this investigation did not include geologic or seismic studies for the site.
Accordingly, our conclusions and recommendations are for static loading conditions only:
however, this does not imply that there is a geologic or seismic hazard affecting the site.
Our recommendations are based on the results of our current and previous field explorations,
laboratory tests, and appropriate engineering analyses. The results of the current and previous field
explorations and laboratory tests, which form the basis of our recommendations, are presented in
Appendix A.
Our professional services have been performed using that degree of care and skill ordinarily
exercised, under similar circumstances, by reputable geotechnical consultants practicing in this or
similar localities. No other warranty, expressed or implied, is made as to the professional advice
included in this report. This report has been prepared for Griffin Realty SA, Inc. and their design
consultants to be used solely in the design of the proposed Planning and Building Agency
building. The report has not been prepared for use by other parties, and may not contain sufficient
information for purpose of other parties or other uses.
2.0 PROJECT DESCRIPTION
Griffin Really SA plans to redevelop a portion of the civic center area for the Public Works
Agency and the Planning and Building Agency following the relocation of the City Police
Department into new facilities. It is planned to demolish the former Police Department building at
the site and construct a new Planning and Building Agency building totaling approximately 30,000
gross square feet. The location of the proposed building has not been determined, however, the
proposed building is anticipated to be two stories above grade. The proposed building may be
underlain by one subterranean level that will utilize and extend beyond the existing basement of
the Police Department building.
2
Grifin Really SA, Inc.-Geotechnical Investigation
Unv/Crandall Project 70131-7-0261.0001
July 8, 1997
3.0 SITE CONDITIONS
The site is located northeast of the Santa Ana City Hall building in the Civic Center area. The site
is currently occupied by the former Police Department building and a surface parking lot. The
Police Department building is currently vacant and is two stories high and underlain by one
subterranean level. The existing building extends over a ramp that connects the existing grade to a
subterranean parking level that is located adjacent to the west side of the existing building. If a
subterranean parking level is not constructed, the existing basement will be backfilled. The
existing building is supported on pile foundations and we understand that the existing piles wili be
left in-place and will not to be used for support of the proposed building. An on grade annex
building is located at the southwest corner ofthe existing building.
4.0 EXPLORATIONS AND LABORATORY TESTS
The soil conditions beneath the site were explored by drilling two borings to depths of 68'h and 70
feet below the existiAg grade at the locations shown in Figure 1. Data were also available from our
previous investigation at the site (our Job No. 58338). Details of the current and prior explorations
and the logs of the borings are presented in the Appendix A.
Laboratory tests were performed on selected samples obtained from the borings to aid in the
classification of the soils and to determine the pertinent engineering properties of the foundation
soils. The following tests were performed:
• Moisture content and dry density determinations.
• Direct shear.
• Consolidation.
• Hydroconsolidation.
• Compaction.
All testing was done in general accordance with applicable ASTM specifications. Details of the
laboratory testing program and test results are presented in the Appendix.
3
Gri#in Realty SA, Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8,1997
5.0 SOIL CONDITIONS'
Fill soils, 2 and 3 feet thick, were found in the two current borings. The fill soils consist of silty
sand and are not uniformly well compacted. Deeper fill could occur between borings and
especially adjacent to the existing basement walls.
The natural soils consist of silly sand, sandy silt, clayey silt, and sand. The silty soils throughout
the depth explored are variable in strength and compressibility, ranging from soft and
compressible to medium stiff. The upper silty soils will become weaker and more compressible
when wet. The sand and silty sand deposits are generally dense.
Water was encountered at depths of 65'/1 and 67'6 feet below the existing grade.
The corrosion studies indicate that the on-site soils are moderately corrosive to ferrous metals and
non-deleterious to Portland cement concrete. The report of corrosion studies presented in
Appendix B should be referred to for a discussion of the corrosion potential of the soils, and for
potential mitigation measures.
6.0 RECOMMENDATIONS
The existing fill soils are not considered suitable for support of the proposed building foundations
and floor slab. The natural silty soils at the site are soft to medium stiff and compressible. Because
of settlement considerations, the use of conventional spread footings is not recommended for the
support of the proposed building. Accordingly, we recommend that the proposed building be
supported on drilled cast-in-place friction piles. If the recommendations on grading are followed,
the floor slab can be supported on grade.
If a subterranean level is to be constructed, excavation of about 15 feet below the existing grade
will be required. The excavation should be either sloped back and/or shored. Care should be taken
in excavating adjacent to the existing buildings to the west to avoid undermining the existing
footings and slabs.
4
Griffin Realm SA, inc.-Geotechnical Investigation
Law/Crandal! Project 70131-7-0261.0001
July 8, 1997
..
6.1 FOUNDATIONS
Drilled Pile Capacities
The downward and upward capacities 6f 18-, 24-, and 30-inch-diameter drilled piles are presented
as a function of penetration below pile caps in Figure 2, Drilled Pile Capacities. Dead plus live
load capacities are shown; a one-third increase may be used for wind or seismic loads. The
capacities presented are based on the strength of the soils; the compressive and tensile strength of
the pile sections should be checked to verify the structural capacity of the piles.
Piles in groups should be spaced at least 20 diameters on centers. If the piles are so spaced, no
reduction in the downward capacities need be considered due to group action.
Settlement
Although foundation load information is not available, we estimate the settlement of the proposed
building, supported on drilled piling in the manner recommended, will be less than 'h inch.
Differential settlement between adjacent columns is expected: to be about 'A inch or less.
Lateral Loads
Lateral loads can be resisted by the piles, by soil friction on the floor slab, and by the passive
resistance of the soils. The soils adjacent to a 24-inch-diameter pile, at least 20 feet long, can resist
horizontal loads imposed at the top of the pile of up to 20,000 pounds. The lateral resistance of
other sizes of piles may be assumed to be proportional to the diameter.
In calculating the bending moment in a pile, the lateral load imposed at the top of the pile may be
multiplied by a moment arm of 5 feet. For design, it may be assumed that the maximum bending
moment will occur near the top of the pile and that the moment will decrease to zero at a depth of
20 feet below the pile cap. The lateral capacity and reduction in the bending moment are based in
part on the assumption that any required backfill adjacent to the pile caps and grade beams will be
properly compacted.
5
Grifin Really SA, Inc.-Geolechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8. 1997
A coefficient of friction of 0.4 can be used between the fioor slab and the supporting soils. The
passive resistance of natural soils or properly compacted fill soils can be assumed to be equal to
the pressure developed by a fluid with a density of 300 pounds per cubic foot. A one-third increase
in the passive value can be used for wind or seismic loads. The frictional resistance and the
passive resistance of the soils can be combined without reduction in determining the total lateral
resistance.
Installation
All drilled pile excavations should be observed by personnel of our firm. Because of the sandy
soils, minor difficulties should be anticipated in drilling the pile shafts because of caving. Water
was encountered at depths of 65'/1 and 67'/1 feet below grade. Accordingly, pile tip evaluations will
be established above the water level. Also, due to the sandy layers, localized water seepage zones
may occur above the groundwater levels encountered in our exploration borings.
Depending on the typeof drilling equipment used by the contractor, some caving and raveling will
occur within the pile shafts during drilling. Precautions should be taken during the installation of
the piles to reduce caving and raveling. Among other precautions, the drilling speed should be
reduced as necessary to minimize vibration and sioughing of the sand deposits.
Closely spaced piles should be drilled and filled alternately, with the concrete permitted to set at
least eight hours before drilling an adjacent hole. Pile excavations should be filled with concrete as
soon after drilling and inspection as possible; the holes should not be left open overnight. The
concrete should be placed with special equipment so that the concrete is not allowed to fall freely
more than 5 feet and to prevent concrete from striking the walls of the excavations.
Spread Footings for Minor Structures
Spread footings, for minor structures, established in the undisturbed natural soils andjor properly
compacted fill soils may be designed to impose a net dead plus live load pressure of 2,000 pounds
per square foot. A one-third increase in the quoted bearing value may be used when considering
6
Grijlin Really SA, Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8. 1997
wind of seismic loads. Footings should extend at least 2 feet below the adjacent final grade. Since
the recommended bearing value is a net value, the weight of concrete within the footings may be
taken as 50 pounds per cubic foot, and the weight of soil backfill may be neglected when
determining the downward load on the footings.
A coefficient of friction of 0.4 can be used between the floor slab and the supporting soils. The
passive resistance of natural soils or properly compacted fill soils can be assumed to be equal to
the pressure developed by a fluid with a density of 300 pounds per cubic foot. A one-third increase
in the passive value can be used for wind or seismic loads. The frictional resistance and the
passive resistance of the soils can be combined without reduction in determining the total lateral
resistance.
6.2 SITE COEFFICIENT AND SEISMIC ZONATION
The site coefficient, S, can be determined as established in the Earthquake Regulations under
Section 1628 of the Uniform Building Code, 1994 edition, for seismic design of the proposed
building. Based on a review of the local soil and geologic conditions, the site can be classified as
Soil Profile S2, and the site coefficient (S) can be taken as equal to a value of 1.2, as specified in
the code. The site is located within UBC Seismic Zone 4.
6.3 EXCAVATION AND SLOPES
Excavation of about 15 feet deep will be required for the basement level. Where the necessary
space is available, temporary unsurcharged embankments may be sloped back at 1: 1 without
shoring. Where space is not available, shoring will be required. Data for design of shoring are
presented in a following section.
The excavations should be observed by personnel of our firm so that any necessary modifications
based on variations in the soil conditions encountered can be made. All applicable safety
requirements and regulations, including OSHA regulations, should be met.
7
Grifin Realry SA, inc.-Geotechnical Investigation
tizw/Crandall Project 70131-7-0261.0001
July 8. 1997
Where sloped embankments are used, the tops of the slopes should be barricaded to prevent
vehicles and storage loads within 5 feet of the tops of the slopes. A greater setback may be
necessary when considering heavy vehicles, such as concrete trucks and cranes; we should be
advised of such heavy vehicle loadings so that specific setback requirements can be established. If
the temporary construction embankments are to be maintained during the rainy season, berms are
suggested along the tops of the slopes where necessary to prevent runoff water from entering the
excavation and eroding the slope faces. The soils exposed in the cut slopes should be inspected
during excavation by our personnel so that modifications of the slopes can be made i f variations in
the soil conditions occur or if adverse water seepage conditions are developed.
6.4 SHORING
General
Where there is not sufficient space for sloped embankments, shoring will be required. One method
of shoring would consist of cantilevered steel soldier piles placed in drilled holes and backfilled
with concrete. The soldier piles can also be retained with drilled-in earth anchors or raker bracing.
Caving and raveling of the granular soils should be considered during installation of the soldier
piles. Special techniques and measures may be necessary in some areas to permit the proper
installation of the soldier piles.
The following information on the design and installation of the shoring is as complete as possible
at this time. We can furnish additional required data as the design progresses. Also, we suggest
that our firm review the final shoring plans and specifications prior to bidding or negotiating with
a shoring contractor.
Lateral Pressures
For design of cantilevered shoring, a triangular distribution of lateral earth pressure may be used.
It may be assumed that the retained soils with a level surface behind the cantilevered shoring will
exert a lateral pressure equal to that developed by a fluid with a density of 30 pounds per cubic
foot.
8
Gri#in Realty SA, inc.-Geotechnical Investigation
Iiiw/Crandall Project 70131-7-0261.0001
July 8, 1997
For the design of tied-back or braced shoring, we recommend the use of a trapezoidal distribution
of earth pressure. The recommended pressure distribution, for the case where the grade is level
behind the shoring, is illustrated in the following diagram with the maximum pressure equal to
22H in pounds per square foot, where H is the height of the shoring in feet. (Where a combination
of sloped embankment and shoring is used, the pressure would be greater and must be determined
for each combination.)
u )..i//2 //03 //02 4 //r
0.2H
O .
CO
0
M-HEIGHT
OF
0
0.6H
SHORING IN FT. 0
0
0
0
0. 1H
0
//A.//A'//£//90//A'//,0//A \|e- 22H -5,|
(P.S.F.)
In addition to the recommended earth pressure, the upper 10 feet of shoring adjacent to any
vehicular traffic areas should be designed to resist a uniform lateral pressure of 100 pounds per
square foot, acting as a result of an assumed 300 pounds per square foot surcharge behind the
shoring due to vehicular traffic. If the traffic is kept back at least 10 feet from the shoring, the
traffic surcharge may be neglected.
Design of Soldier Piles
For the design of soldier piles spaced at least two diameters on centers, the allowable lateral
bearing value (passive value) of the soils below the level of excavation may be assumed to be 500
pounds per square foot per foot of depth, up to a maximum of 2,000 pounds per square foot. To
develop the full lateral value, provisions should be taken to assure firm contact between the soldier
piles and the undisturbed soils. The concrete placed in the soldier pile excavations may be a lean-
mix concrete. However, the concrete used in that portion of the soldier pile which is below the
9
Grifin Realty SA, Inc.-Geotechnical Investigation
Uiw/Crandall Project 70131-7-0261.0001
July 8. 1997
planned excavated level should be of sufficient strength to adequately transfer the imposed loads
to the surrounding soils.
The frictional resistance between the soldier piles and the retained earth may be used in resisting
the downward component of the anchor load. The coefficient of friction between the soldier piles
and the retained earth may be taken as 0.4. (This value is based on the assumption that uniform
full bearing will be developed between the steel soldier beam and the lean-mix concrete and
between the lean-mix concrete and the retained earth.) In addition, provided that the portion of the
soldier piles below the excavated level is backfilled with structural concrete, the soldier piles
below the excavated level may be used to resist downward loads. The frictional resistance between
the concrete soldier piles and the soils below the excavated level may be taken as equal to 400
pounds per square foot.
Lagging
Continuous lagging will be required between the soldier piles. The soldier piles and anchors
should be designed for the full anticipated lateral pressure. However, the pressure on the lagging
will be less due to arching in the soils. We recommend that the lagging be designed for the
recommended earth pressure but limited to a maximum value of 400 pounds per square foot.
Anchor Design
Tie-back friction anchors may be used to resist lateral loads. For design purposes, it may be
assumed that the active wedge adjacent to the shoring is defined by a plane drawn at 35 degrees
from the vertical through the bottom of the excavation. The anchors should extend at least 15 feet
beyond the potential active wedge and to a greater length if necessary to develop the desired
capacities.
The capacities of anchors should be determined by testing of the initial anchors as outlined in a
following section. For design purposes, it may be estimated that drilled friction anchors will
develop an average friction value of 600 pounds per square foot. Only the frictional resistance
developed beyond the active wedge would be effective in resisting lateral loads. If the anchors are
10
Grifin Realty SA, Inc.-Georechnical Investigation
L,aw/Crandall Project 70131-7-0261.0001
July 8, 1997
spaced at least 6 feet on centers, no reduction in the capacity of the anchors need be considered
due to group action.
Anchor Installation
The anchors may be installed at angles of 15 to 40 degrees below the horizontal. Caving of the
anchor holes should be anticipated and provisions made to minimize such caving.
The anchors should be filled with concrete placed by pumping from the tip out, and the concrete
should extend from the tip of the anchor to the active wedge. To minimize chances of caving, we
suggest that the portion of the anchor shaft within the active wedge be backfilled with sand before
testing the anchor. This portion of the shaft should be filled tightly and flush with the face of the
excavation. The sand backfill may contain a small amount of cement to allow the sand to be
placed by pumping.
Anchor Testing
Our representative should select at least one of the initial anchors for a 24-hour 200% test, and two
additional anchors for quick 200% tests. The purpose of the 200% tests is to verify the friction
value assumed in design. The anchors should be tested to develop twice the assumed friction
value. Anchor rods of sufficient strength should be installed in these anchors to support 200% test
loading. Where satisfactory tests are not achieved on the initial anchors, the anchor diameter
and/or length should be increased until satisfactory test results are obtained.
The total defiection during the 24-hour 200% tests should not exceed 12 inches during loading; the
anchor deflection should not exceed 0.75 inch during the 24-hour period, measured after the 200%
test load is applied. If the anchor movement after the 200% load has been applied for 12 hours is
less than 0.5 inch, and the movement over the previous 4 hours has been less than 0.1 inch, the test
mav be terminated.
Ill----Ill=/
11
Griffin Really SA, Inc.-Geotechnical Investigation
I.aw/Crandall Project 70131-7-0261.0001
July 8, 1997
For the quick 200% tests, the 200% test load should be maintained for 30 minutes. The total
deflection of the anchor during the 200% quick test should not exceed 12 inches; the deflection
after the 200% test load has been applied should not exceed 0.25 inch during the 30-minute period.
All of the production anchors should be pretested to at least 150% of the design load; the total
deflection during the tests should not exceed 12 inches. The rate of creep under the 150% test
should not exceed 0.1 inch over a 15-minute period for the anchor to be approved for the design
loading.
After a satisfactory test, each production anchor should be locked-off at the design load. The
locked-off load should be verified by rechecking the load in the anchor. If the locked-off load
varies by more than 10% from the design load, the load should be reset until the anchor is locked-
off within 10% of the design load.
The installation of the anchors and the testing of the completed anchors should be observed by our
firm.
Internal Bracing
Raker bracing, if used, could be supported laterally by temporary concrete footings (deadmen).
For design of such temporary footings, poured with the bearing surface normal to rakers inclined
at 45 to 60 degrees with the vertical, a bearing value of 2,000 pounds per square foot may be used
· at the excavation level, provided the shallowest point of the footing is at least 1 foot below the
lowest adjacent grade. To reduce the movement of the shoring, the rakers should be preloaded or
at least tightly wedged between the footings and the soldier piles.
Dellection
It is difficult to accurately predict the amount of deflection of a shored embankment. It should be
realized, however, that some dellection will occur. We estimate that this deflection would be less
than 1 inch at the top of a cantilevered shoring system, and less than M inch for a braced shoring
system. If greater dellection occurs during construction, additional bracing may be necessary to
12
Grifin Realty SA, Inc.-Geotechnical Investigation
Unv/Crandall Project 70131-7-0261.0001
July 8, 1997
minimize settlement of the adjacent structures. If desired to reduce the deflection of the shoring, a
greater active pressure could be used in the shoring design.
Monitoring
Some means of monitoring the performance of the shoring system is recommended. The
monitoring should consist of periodic surveying of the lateral and vertical locations of the tops of
all the soldier piles and the lateral movement along the entire lengths of selected soldier piles.
Also, some means of periodically checking the load on selected anchors may be necessary. We
will be pleased to discuss this further with the other design consultants and the contractor when the
design ofthe shoring system has been finalized.
6.5 WALLS BELOW GRADE
Lateral Pressures
For design of cantilevered retaining walls below grade where the surface of the backfill is level, it
may be assumed that the soils will exert a lateral pressure equal to that developed by a fluid with a
density of 30 pounds per cubic foot.
The building walls below grade should be designed to resist a trapezoidal distribution of lateral
earth pressure plus surcharges from adjacent loads. The lateral earth pressure on the permanent
walls below grade will be the same as that recommended for design of temporary shoring with a
maximum lateral pressure will be 22H in pounds per square foot, where H is the height of the wall
in feet.
In addition to the recommended earth pressure, the upper 10 feet of walls adjacent to any vehicular
traffic areas should be designed to resist a uniform lateral pressure of 100 pounds per square foot,
acting as a result of an assumed 300 pounds per square foot surcharge behind the walls due to
normal traffic. If the traffic is kept back at least 10 feet from the walls, the traffic surcharge may
be neglected.
13
Gri#in Realry SA, Inc.-Geotechnical investigation
Law/Crandall Project 70131-7-0261.0001
July 8, 1997
Backfill
Any required soil backfill should be mechanically compacted, in layers not more than 8 inches in
thickness. to at least 90% of the maximum dry density obtainable by the ASTM Designation
Dl 557-91 method of compaction. The on-site soils may be used in the backfill. Flooding should
not be permitted. Proper compaction of backfill will be necessary to reduce settlement of the
backfill and to reduce settlement of overlying walks and paving.
Some settlement of the backfill should be anticipated, and any utilities supported therein should be
designed to accept differential settlement, particularly at the points of entry to the building. Also,
provisions should be made for some settlement of concrete walks on grade supported on backfill.
Drainage
Walls below grade and retaining walls should be designed to resist hydrostatic pressures or be
provided with drain pipes or weepholes. A drain pipe could consist of a 4-inch-diameter perforated
pipe placed with perforations down at the base of the wall. The pipe should be sloped at least 2
inches in 100 feet and surrounded by filter gravel. The filter gravel should meet the requirements
of Class 2 Permeable Material as defined in the current State of California, Department of
Transportation, Standard Specifications. If Class 2 Permeable Material is not available, 4-inch
crushed rock or gravel separated from the on-site soils by an appropriate filter fabric, such as
Mirafi 140 or equivalent, can be used. The crushed rock or gravel should have less than 5%
passing a No. 200 sieve. For exterior retaining walls, drainage can be provided by weepholes
placed about 10 feet on center.
6.6 FLOOR SLAB SUPPORT
If the subgrade is prepared as recommended in the following section on grading, the building floor
slab can be supported on grade. Construction activities and exposure to the environment can cause
deterioration of the prepared subgrade. Therefore, we recommend that our field representative
observe the condition of the final subgrade soils immediately prior to slab-on-grade construction,
and, if necessary, perform further density and moisture content tests to determine the suitability of
the final prepared subgrade.
14
Griffin Realty SA. Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8, 1997
I f vinyl or other moisture-sensitive floor covering is planned, we recommend that the floor slab in
those areas be underlain by a capillary break consisting of a vapor-retarding membrane over
a 4-inch-thick layer of gravel. Two-inch-thick layers of sand should be placed above and below the
membrane to decrease the possibility of damage to the membrane and reduce slab curling. We
suggest the following gradation for the gravel:
Sieve Size Percent Passing
%4"90-100
No. 4 0-10
No. 100 0-3
A low-slump concrete should also be used to minimize possible curling of the slab. Care should be
taken during the placement of the concrete to prevent displacement of the sand. The concrete slab
should be allowed to cure properly before placing vinyl or other moisture-sensitive floor covering.
6.7 PAVING
An R-value of 20 was assumed for design of asphalt paving based on our observations and
experience with similar soil conditions. The R-value should be confirmed during grading.
Assuming that the paving subgrade will consist of the on-site or comparable soils compacted to at
least 90% as recommended in the following section on grading, the minimum recommended
paving thicknesses are presented in the following tables. The asphalt paving sections were
determined using the flexible pavement design procedure used by the Orange County
Environmental Management Agency. The Portland Cement Concrete (PCC) paving sections were
determined using the Portland Cement Association design method; base course beneath the PCC
paving is not required.
15
Griffin Really SA, Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8, 1997
Asphalt Concrete Paving
Asphalt Concrete Base Course
Traffic Use Traffic Index (inches)(inches)
Automobile Parking 4.0 3 4
Drives Subject to 5.5 3 10
Light Truck Traffic
Drives Subject to 7.0 4 13
Heavy Truck Traffic
Portland Cement Concrete Paving
Portland Cement
Traffic Use Traffic Index Concrete (inches)
Automobile Parking 4.0 7
Drives Subject to 5.5 7%
Light Truck Traffic
Drives Subject to 7.0 8
Heavy Truck Traffic
We can determine the recommended paving and base course thicknesses for other Traffic Indices
if required. Careful inspection is recommended to verify that the recommended thicknesses or
greater are achieved, and that proper construction procedures are followed.
The base course should conform to requirements of Section 26 of State of California Department
of Transportation Standard Specifications (Caltrans), latest edition, or meet the specifications for
untreated base as defined in Section 200-2 of the latest edition of the Standard Specifications for
Public Works Construction (Green Book). The base course should be compacted to at least 95%.
6.8 GRADING
The existing fill soils were not observed and tested during placement and are not considered
suitable for support of foundations, paving, or slabs on grade. The existing fill soils should be
excavated and replaced as properly compacted fill. All required fill should be uniformly well
compacted and observed and tested during placement. The on-site soils can be used in any
required fill. If a basement is not planned. the existing basement should be backfilied. However.
16
Griffin Realty SA. Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8.1997
prior to backfilling, holes 2 to 3 inches in diameter and spaced at 10 feet on centers should be
cored through the floor slab of the existing basement.
Site Preparation
After the site is cleared and existing fill soils are excavated as recommended, the exposed natural
soils should be carefully observed for the removal of all unsuitable deposits. Next, the exposed
soils should be rolled with heavg compaction equipment. At least the upper 6 inches of the
exposed soils should be compacted to at least 90% of the maximum dry density obtainable by the
ASTM Designation D 1557-91 method of compaction.
Compaction
Any required fill should be placed in loose lifts not more than 8 inches thick and compacted. The
fill should be compacted to at least 90% of the maximum density obtainable by the ASTM
Designation D1557-91 method of compaction. The moisture content of the on-site soils at the time
of compaction should vary no more than 2% below or above optimum moisture content.
Material for Fill
The on-site soils, less any debris or organic matter, can be used in required fills. Cobbles larger
than 4 inches in diameter should not be used in the fill. Any required import material should
consist of relatively non-expansive soils with an expansion index of less than 35. The imported
materials should contain sufficient fines (binder material) so as to be relatively impermeable and
result in a stable subgrade when compacted. All proposed import materials should be approved by
our personnel prior to being placed at the site.
6.9 GEOTECHNICAL OBSERVATION
The reworking of the upper soils and the compaction of all required fill should be observed and
tested during placement by a representative of our firm. This representative should perform at least
the following duties:
17
Griffin Really SA. Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8. 1997
• Observe the clearing and grubbing operations for proper removal of all
unsuitable materials.
• Observe the exposed subgrade in areas to receive fill and in areas where
excavation has resulted in the desired finished subgrade. The representative
should also observe proofrolling and delineation of areas requiring
overexcavation.
• Evaluate the suitability of on-site and import soils for fill placement; collect
and submit soil samples for required or recommended laboratory testing
where necessary.
• Observe the fill and backfill for uniformity during placement.
• Test backfill for field density and compaction to determine the percentage of
compaction achieved during backfill placement.
• Observe the drilling and pouring of the piles to verify that the desired
diameter and depth are obtained.
• Observe and probe foundation materials to confirm that suitable bearing
materials are present at the design foundation depths.
The governmental agencies having jurisdiction over the project should be notified prior to
commencement of grading so that the necessary grading permits can be obtained and arrangements
can be made for required inspection(s). The contractor should be familiar with the inspection
requirements ofthe reviewing agencies.
7.0 BASIS FOR RECOMMENDATIONS
The recommendations provided in this report are based upon our understanding of the described
project in formation and on our interpretation of the data collected during our current and previous
subsurface explorations. We have made our recommendations based upon experience with similar
subsurface conditions under similar loading conditions. The recommendations apply to the
specific project discussed in this report; therefore, any change in the structure configuration, loads,
location, or the site grades should be provided to us so that we can review our conclusions and
recommendations and make any necessary modifications.
18
Grillin Really SA, Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 8, 1997
The recommendations provided in this report are also based upon the assumption that the
necessary geotechnical observations and testing during construction will be performed by
representatives of our firm. The field observation services are considered a continuation of the
geotechnical investigation and essential to verify that the actual soil conditions are as expected.
This also provides for the procedure whereby the client can be advised of unexpected or changed
conditions that would require modifications of our original recommendations. In addition, the
presence of our representative at the site provides the client with an independent professional
opinion regarding the geotechnically related construction procedures. If another firm is retained
for the geotechnical observation services, our professional responsibility and liability would be
limited to the extent that we would not be the geotechnical engineer of record.
19
1
1
1
1
1
1
1
1
FIGURES
1
1
1
1
1
1
1
1
1
EXISTING EXISTING
ANNEX SUBTERRANEAN
BLDG.PARKING
(TO REMAIN)(TO REMAIN)
,
1 T----,
/ 2
1
EXISTING BLDG. 1
[TO BE DEMOLISHED)lg/
1 El
1 \ .0- '-
k
1 1 1 1
1
1
2 ili
'A .0 1-1101
1
l
11 <
m I
1
-I--TO SANTA ANA BLVD. 1 1 TO CIVIC CTR. DR.
1 1
1 1
ROSS ST.
B.M FOR BOR. ELEVS
CHISELED W IN SIDEWALK
ASSUMED EL .100.00
MEI:
2 CURRENT INVESTIGATION
(70131-7-0261.0001)
1 Q PREVIOUS INVESTIGATION
(58338)
- BORING LOCATION
AND NUMBER
SITE PLAN
SCALE 1 = 40'
LAW/CRANDALL ,
FIGURE 1
JOB 7013/-7-0241.
000<
DATE F -25- 47
F.T.
DR. rl·A.
O.E.
CHKD
W
0
0
ALLOWABLE DOWNWARD PILE CAPACITY in Kips
40 80 120 160 200 240
/-- Pile Diameter in Inches
0
(18 267*2
\\ 1-00
1·U - -
0 20 40 60 80 100 120
ALLOWABLE UPWARD PILE CAPACITY in Kips
NOTES:
(1) The indicated Mlues refer to the total of dead plus INe loads; a one-third increase may be
used when considering wind or seismic loads.
(2) Piles in groups should be spaced a minimum of 2-1/2 diameters on centers, and should be
drilled and filled alternately with the concrete permitted to set at least 8 hours before drilling
an adjacent hole.
(3) The indicated Malues are based on the strength of the soils; the actual pile capacities may
be limited to lesser yalues by the strength of the piles.
DRILLED PILE CAPACITIES
LAW/CRANDALL n
FIGURE 2
JOB 70131.70261.0001 DATE : 6/26/97
OE.
mwh
CHKD:PENETRATION BELOW PILE CAP in Feet
1
1
1
1
1
1
1
1
APPENDIX A
EXPLORATIONS AND LABORATORY TESTS
1
1
1
1
1
1
1
1
1
Gri#in Really SA. Inc.-Geotechnical Investigation
Law/Crandall Project 70131-7-0261.0001
July 7,1997
APPENDIX A
EXPLORATIONS AND LABORATORY TESTS
EXPLORATIONS
The soil conditions beneath the site were recently explored by drilling two borings. In addition,
data were available from our prior investigation at the site (our Job No. 58338). The locations of
our current and prior borings are shown in Figure 1. The current borings were drilled to depths of
68% and 70 feet below the existing grade using 18-inch-diameter bucket-type drilling equipment.
Caving and raveling of the boring walls occurred as indicated on the boring logs; however, easing
or drilling mud was not used to extend the borings to the depths drilled.
The soils encountered were logged by our field technician, and undisturbed and bulk samples were
obtained for laboratory inspection and testing. The logs of the current borings are presented in
Figures A-1.1 through A-1.2; the logs from prior borings are presented in Figures A-1.3 and A-
1.5. The depths at which the undisturbed samples were obtained are indicated to the left of the
boring logs. The number of blows required to drive the Crandall sampler 12 inches is indicated on
the logs. The soils are classified in accordance with the Unified Soil Classification System
described in Figure A-2.
LABORATORY TESTS
Laboratory tests were performed on selected samples obtained from the borings to aid in the
classification of the soils and to determine their engineering properties.
The field moisture content and dry density of the soils encountered were determined by
performing tests on the undisturbed samples. The results of the tests are shown to the left of the
boring logs.
A-1
Griffin Realry SA, Inc.-Geotechnical Investigation
Inw/Crandall Project 70131-7-0261.0001
July 7,1997
Direct shear tests were performed on selected undisturbed samples to determine the strength of the
soils. The tests were performed at field moisture content and after soaking to near-saturated
moisture content and at various surcharge pressures. The yield-point values determined from the
direct shear tests are presented in Figure A-3, Direct Shear Test Data.
Confined consolidation tests were performed on two undisturbed samples to determine the
compressibility of the soils. Water was added to one of the samples during the tests to illustrate the
effect of moisture on the compressibility. The results of the tests are presented in Figures A-4,
Consolidation Test Data.
The optimum moisture content and maximum dry density of the upper soils were determined by
performing a compaction test on a sample obtained from Boring 1. The test was performed in
accordance with the ASTM Designation D1557-91 method of compaction. The results of the tests
are presented in Figure A-5, Compaction Test Data.
In addition to the normal consolidation tests, a "quick" consolidation test was performed on an
undisturbed sample to determine the hydroconsolidation potential of the soils. The test was
performed by confining the sample under a normal surcharge pressure, allowing the sample to
consolidate at its field moisture content, and then saturating the sample and measuring the
consolidation resulting from the addition of water. The results (percent hydroconsolidation) of the
test are presented in Figure A-6, Hydroconsolidation Test Data.
4
A-2
EB
D>EVATION Hld3a BORING 1
LU
DATE DRILLED:June 5,1997
EQUIPMENT USED: 18" - Diameter Bucket
ELEVATION:100.6 ./
100 -
4
SM
2.8 102 2 . IE Ili
3" Asphalt Paving
FILL - SILTY SAND - fine, pieces of concrete and metal, light
brown
SURFACE OF NATURAL SOIL
SILTY SAND - fine, brown
5 t' lit
95 -
- 10
90 -
1(Ki· sp-SAND and SILTY SAND - fine, light brown
3.0 99 3 'intil SM
Wn
1.0 95 2 .OV;
1 ML SANDY SILT - some Clay, few Gravel, brown
10.3 102 2 1
- 15
85 -7.0 105 2 1 CLAYEY SILT - some Sand, brownML
17.9 108 3 1
- 20
80 -
7.4 111 2 1 Layers of Sandy Silt
- 25 20.2 101 2 1 ML SANDY SILT - some Clay, light greyish brown
75 -
15.8 109 9 1 Brown
* Number of blows required to drive the Crandall sampler 12
inches for depths of:
- 30 0' to 25' using a 1600 pound hammer falling 12 inches;
70 -10.7 111 10 1 25' to 50' using an 800 pound hammer falling 12 inches;
Below 50' using a 1200 pound hammer falling 12 inches.
* * Elevations refer to assumed datum; see Figure 1 for location
and elevation of bench mark.
12.3 97 11- 35
65 -Layer of fine Sand, brown
10.740
J013 Not
118 5 1 Few Gravel, brown
(CONTINUED ON FOLLOWING FIGURE)
LOG OF BORING
LAW/CRANDALL
FIGURE A-1.la
e: The log of subsurface conditions shown hereon applies only at the specific boring location and at the date indicated 11 is not warranted to be representative of subsurface conditions at other locations and times.
I D>ATION llSN3 2 2=
- D=
5 0:
O 09
ELEV 30
BORING 1 (Continued)
DATE DRILLED:June 5, 1997
EQUIPMENT USED: 18" - Diameter Bucket
ELEVATION:100.6 **
60 -
45
SAND - fine, some Gravel, few Cobbles (to 5" in size), lightD ..brown22: i
20
t.ip:
ML SANDY SILT - brown
50 20.5 108 6 1
ML CLAYEY SILT - brown
55 16.1 116 4 1
Layer of Sandy Silt
19.3 114 11 /-,7,-----60 .N : SM SILTY SAND - fine to medium, about 20% Gravel, brown
R bt
A :.13 Sw SAND - well graded, light brown
2.9 114 14 1 2··.3 -65
:d '.
ML CLAYEY SILT - some Sand, brown
70 24.5 101 17 1
(BORING TERMINATED AT A DEPTH OF 70' DUE TO LACK OF
PROGRESS)
NOTE: Water level measured at a depth of 65 !4' 15 minutes after
completion of drilling. Caving from 6' to 10' (to
3' in diameter) and below 6614'
LOG OF BORING
LAW/CRANDALL
FIGURE A-l.lb
I JCIO 131_I DI/25 GIV M-C 'Note: The log of subsurface conditions shown hereon applies only at the specific boring location and at the date indicated.It is not wairanted to be representative of subsurface conditions at other locations and times.W Ull
0
u'l
1
1
50 -
55 -
D>EVATION Hld30
UJ
to
0 -
Z =i
U.1 0
Oh
Z-
3 45
O -Di
0 23
BORING 2
DATE DRILLED:June 10,1997
EQUIPMENT USED: 18" - Diameter Bucket
ELEVATION:103.1
@li
100 -
8.1 129 12
3" Asphalt Paving - 7" Base Course
:, SM FILL - SILTY SAND - fine, some pieces of brick and metal,
light brown
SURFACE OF NATURAL SOIL
ML SANDY SILT - some Clay, few roots, brown
-5 2 2 2 SM SILTY SAND - fine, brown
2.1 102 2 1
95 -
4.5 103 2 Light brown- 10 ...
ML SANDY SILT - few roots, light brown
9.9 93 2 1 Rootlets
90 -
15
9.9 110 3 1 Brown
85 -
14.9 97 3 1
- 20
12.5 105 4 1 Rootlets
80 -
- 25 14.9 110 3 1
12.5 98 9 1
75 -
- 30
13.4 106 8 1 Some Clay
70 -
- 35 10.2 102 8 1
65 -
40
Some Clay
18.6 104 12 i.-:--
(CONTINUED ON FOLLOWING FIGURE)
LOG OF BORING
LAW/CRANDALL
FIGURE A-1.2a
11111 11111 J(11111
013
/////61 ///// DA16/25 GIVII DR M CI Note: The log of subsurface conditions shown hereon applies only at the specific boring location and at the date indicated.It is not warranted to be representative of subsurface conditions at other locations and times.
0 2% L.
g- E- 22 z.
ELEV
5 2 9 BORING 2 (Continued)
0: w
0% rl
9 2 * DATE DRILLED:June 10,1997
O 2 4 EQUIPMENT USED: 18" -Diameter Bucket
@ in ELEVATION:103.1
60 -
Layer of Silty Sand
SP SAND - fine, light brown
Layer of Sandy Silt
1.5 119 17 1%41
A.
Few Cobbles (to 8" in size)
1.9 118 15 Fine to coarse, light brown
ML CLAYEY SILT - brown
20.7 106 3 I
18.8 113 5 1 SANDY SILT - some Clay, brownML
26.1 101 11 1
Layer of Silty Sand
SW SAND - well graded, about 20% Gravel and Cobbles, light greyish
brovvn
END OF BORING AT 68 M'
NOTE: Water seepage encountered at 67 72'. Water level measured
at a depth of 67 h' 30 minutes after completion of
drilling. Heavy caving and raveling from 47' to 51'
and from 67!4' to 68/2' (to 3' in diameter).
LOG OF BORING
LAW/CRANDALL
FIGURE A-1.2b
--J
€01361 DA6/25 GA/ DR. . M Cl Note: The log of subsurface conditions shown hereon applies only at the specific boring location and at the date indicated.It is not warranted to be representative of subsurface conditions at other locations and times.CO
Ul
N
U1
0
Ul
0
1
1
1
1
99 -
09 -
- 55
- 50
55 -
- 45
11.-L-
16 "-Diameter Ro* Buckit Hole
Drilled October 1, 1958
0
Elevatian 102.4*
100-5.1*- 911. in SILTY 8AND - sant predaninantly fine, contains
large amount of ailt, brown
.
6.4%. 86 :f f f Sand fine to very fine, medium amount of
silt, light brown
11.0*- 9413; f Sand predaminantly very fine, contain•
10 large amount of Bilt
90-
15·00- 95 1
14 - 10-106 i N .
•20
80-
- 25.80- 96 1
Grading to SILT - containg small amount of
very fine sand, brown
Small amount of clay
SILTY SAND - sand predominantly very fine,
contains large amount of Bilt, brorn
SILT - contains large amount of clay, plastic,
brown
4 30
-7 SILTY SAND - and predaninantly fine, contains
12.00-104 1-large amount of silt, brown
e Al
0 40
060_ O
-4
)4
5o
50 _
%
-70_
- 34.6%- 84.Layers of ELASTIC SILT and SILT
5.7%-118 i
22.4%-104 1 7,
20.7%-107 1
POORLY GRADED SAND - fine to medium, trace of
fines, fe• gravel, brown
Large amount of gravel, few cobbles to 6"
Grading to WELL GRADED SAND - contains large
amount of gravel and small cobbles, trace
of fines, brain
SILT - cantaine large amount of clay, slightly
plastic, small amount of very fine Band,
fe, amall cobbles, brown
21.5%-101 1
60 15.90-112 '*d p°°=Dg=El; =to medium, large
40-0171 WELL GRADED SAND - contains large eount of
j..,9.1 gravel and cobbles to 10", greyiah-brown
NOTE: Groundwater not encountered; caved badly
fram 42' to 46' and fram 60' to 65'.
15 9%-lf 'Indicates depth at which undisturbed simple
obtained
Dry density in pounds per cubic foot
Field moisture cantent in percent af dry weight
Soils classified in accordance vith the Unified
Soil Classificatian System.
* 11*vatians refer to assumed datum (see Plot Plan
for benchmark).
LEROY CRANDALL O ASSOCIATES
FIGURE A-1.3
JUU
1,Al t
8 Y £ <54
...
4 -
Ca-+
LOG OF BORING 1
LOO OF BORING 2
24"-Diameter Rotary Bucket Hole
Drilled October 2, 1958
Elevation 102.00
100-0 f : SILTY SAND - aand predominantly fine, contains
3.40- 95/62 j i large amount of silt, brown
Small amount of silt
..
21.4%- 81
10
SILT - cantains small amount of clay and
very fine sand, brown
90-22.2%- 98
6.6%-10(*UJ SILTY SAND - sand uredominantly fine, containst.1-medium amount of silt, brown
20 24 Layer of FINE SAND
80- ®64 25. 70- 90:fi 2#Ir-0709*lps115'e amolmt of clay, brown
18.0%-101
Small amount of olay and medium amount of
very fine sand
3o
70 _
60-
,EZ Layers of POORLY GRADED FINE SAND1
6 8.2%-11lliE SILTY SAND and POORLY GRADED FINE SAND
' 40 frht
05.·i: WELL GRADED SAND - containa large amount of
3.2%-1(7:itbi gravel, few small cobbles, trace of silt,
broln
SILT - contains large amount af clay and
22.6%-1031 small amount of very fine sand, brown
5o
50_
17.9%-1111
6o
40-
.0.Small amouu b of gravel and cobbles21. 3%-1031 77 SILTY SAND - sand predominantly fine to very
1, : t.fine, contains large amount of silt
54-' WELL GRADED RAND - cantaing large amount of
gravel and small cobbles, greyish-broin
NOTE: Groundiater not encountered
40, to 44, and 60' to 63'·
; caving from
LEROY CRANDALL 6- ASSOCIATES
FIGURE A-1.4
JUD. --- .--- I. UAIt
8 7 C. « 6 .
Elevation
in
feet
LOG OF BORING 3
24"-Diameter Rot/ry Bucket Hole
Drilled October 1, 1958
100-
Elevatian 101.1
C ·: SILTY SAND - sand predominantly fine, contains
6.7%- 931{ ·:large amount of silt, brown
... 11.
1444 Layer of po0RLY GRADED FINE. SAND
90 10
RE Layer of SILT
5. 3%-102!j. f j Medium amount of silt
F . Small amount of gravel
SILT - contains medium amount of clay and
19.4%-1031 very fine sand, broin
E Layer of POORLY GRADED SAND - fine to
4 20 medium, with gravel80 - 26.0%- 891
o Slightly plastic
21.9%-1011
70 -
60 -
¤ 30
0. 40
A.
7. 3%-114+:-,-cm
2 9:0,
'3:10 g
3.2*-1001 :4 P.
22.5%-1031
Layer of POORLY GRADED SAND - fine to medium
with gravel
Lens of FINE SAND
POORLY GRADED SAND - fine, contains few gravel
and small cobbles, small amount of fines,
bro•n
Sand fine to medium, medium to large amountof gravel and small cobbles
SILT - contains large amount of clay, brown
50 Few small gravel50 _14.0%-1081
40 -
..7.9- \ELL GRADED SAND - contains large amount ofgravel, medium amount of cobbles to 8",
3.60-1151 *W trace of fines, bro•n
60 bif
NOTE: Groundwater not encountered; oeving fram 18'
to 20'; 38' to 45' and 53' to 60'.
LEROY CRANDALL 6- ASSOCIATES
cint *c 8-14
Elevation
in
feet
SHEAR STRENGTH in Pounds per Square Foot
0
0
0
2@6 \
2000
000 2000 3000
/1@12
02@16
01@2,
*1@3
0 1@34
2@6
1 4000 5000 6000
O.1@3
1000 \ BORING NUMBER &
SAMPLE DEPTH (FT.)
02@21
3000 0 222 ju
4000 82¢Z!39
02@54
VALUES USED /
IN ANALYSES
5000
01@54
6000 - '0,@64
KEY
0 Samples tested at field moisture content
2 Samples tested after soaking to a moisture contentnear saturation
4-Natural solls
DIRECT SHEAR TEST DATA
LAW/CRANDALL L.
FIGURE A-3
I JOI'-
131
1 00 DA/18/
R WKD SURCHARGE PRESSURE in Pounds per Square Foot
LOAD IN KIPS PER SQUARE FOOT
0.4
0
0.5 0.6 0.7 0.8 0.91.0 2.0 3.0 4.0 5.0 6.0 7.0
1 1
Boring 2 at 12'
/-- SANDY SILT
0.02
Boring 1 at 49' \
SANDY SILT
-2-
NOTE: Wateradded to sample from Boring 2 afterconsolidation under a load of 3.6 kips per sQuare foot
The other sample tested at field moisture content.
CONSOLIDATION TEST DATA
LAW/CRANDALL
8.0
FIGURE A-4
JOB 70131.70261.0001
DATE 6/26/97
DR JB
0E
MWH
CHKD
CONSOLIDATION IN INCHES PER INCH
0
0
0
0
0
0
0
0
(JO
CD
fL'O
EL O
BORING NUMBER
AND SAMPLE DEPTH:1 at 2' to 5'
SOIL TYPE:SILTY SAND
MA)0MUM DRY DENSITY:126
(lbs./cu. ft.)
OPTIMUM MOISTURE CONTENT:9.5
(% of dry wt.)
TEST METHOD:ASTM Designation D1557-91
COMPACTION TEST DATA
LAW/CRANDALL
FIGURE A -
JOB--70131.70261.0001
|r23/9 0
DAT
JB
MWA-- CHKD
Ul
BORING NUMBER
AND SAMPLE DEPTH:1 at 12'
SOIL TYPE:SANDY SILT
SURCHARGE PRESSURE:3600
(lbs./sq. ft.)
PERCENT HYDROCONSOLIDATION:3.8
HYDROCONSOLIDATION TEST DATA
LAW/CRANDALL
FIGURE A
./ /1:'I
702/9'BFO 1
E : |3/97 MW C
CD
1
1
1
1
1
1
1
1
APPENDIX B
1
SOIL CORROSIVITY STUDY BY M.J. SCH[FF AND
ASSOCIATES
1
1
1
1
1
1
M. J. SCHIFF & ASSOCIATES, INC.
Consulting Corrosion Engineers - Since 1959 1291 North Indian Hill Boulevard
Claremont, California 91711-3897
Phone 909-626-0967
FAX 909-621-1419
E-mail SCHIFFCORR@AOL.COM
June 26,1997
LAW/CRANDALL, INC.
200 Citadel Drive
Los Angeles, California 90040-1554
Attention:Mr. Michael Han
Re:Soil Corrosivity Study
Santa Ana Police Department Building
Santa Ana, California
Your #70131-7-0261.0001, MTS&A #97192
INTRODUCTION
Laboratory tests have been completed on two soil samples we selected from your boring logs for
the referenced police department project. The purpose of these tests was to determine if the soils
may have deleterious effects on underground utilities, hydraulic elevator cylinders, and concrete
foundations. We assume that the samples provided are representative of the most corrosive soils at
the site.
The scope of this study is limited to a determination of soil corrosivity and general corrosion
control recommendations for materials likely to be used for construction. If the architects and/or
engineers desire more specific information, designs, specifications, or review of design, we will be
happy to work with them as a separate phase ofthis project.
TEST PROCEDURES
The electrical resistivity of each sample was measured in a soil box per ASTM G57 in its as-
received condition and again after saturation with distilled water. Resistivities are at about their
lowest value when the soil is saturated. The pH of the saturated samples was measured. A 5:1
water:soil extract from each sample was chemically analyzed for the major anions and cations.
Test results are shown on Table 1.
CORROSION AND CATHODIC PROTECTION ENGINEERING SERVICES
PLANS AND SPECIFICATIONS • FAILURE ANALYSIS • EXPERT WITNESS ' CORROSIVITY AND DAMAGE ASSESSMENTS
LAW/CRANDALL, INC.June 26,1997
MJS&A #97192 Page 2
SOIL CORROSIVITY
A major factor in determining soil corrosivity is electrical resistivity. The electrical resistivity of a
soil is a measure of its resistance to the flow of electrical current. Corrosion of buried metal is an
electrochemical process in which the amount of metal loss due to corrosion is directly proportional
to the flow of electrical current (DC) from the metal into the soil. Corrosion currents, following
Ohm's Law, are inversely proportional to soil resistivity. Lower electrical resistivities result from
higher moisture and chemical contents and indicate corrosive soil.
A correlation between electrical resistivity and corrosivity toward ferrous metals is:
Soil Resistivity
in ohm-centimeters Corrosivity Category
over 10,000 mildly corrosive
2,000 to 10,000 moderately corrosive
1,000 to 2,000 corrosive
below 1,000 severely corrosive
Other soil characteristics that may influence corrosivity towards metals are pH, chemical content,
soil types, aeration, anaerobic conditions, and site drainage.
Electrical resistivities were in mildly and moderately corrosive categories with as-received
moisture. When saturated, both resistivities dropped into the moderately corrosive category.
Soil pH values were 6.4 and 6.5. These values are slightly acidic and do not particularly increase
soil corrosivity.
The chemical content of the samples was low.
Tests were not made for sulfide or negative oxidation-reduction (redox) potentials because they
would not exist in these aerated samples.
This soil is classified as moderately corrosive to ferrous metals.
LAW/CRANDALL, INC.June 26,1997
MJS&A #97192 Page 3
CORROSION CONTROL
The life of buried materials depends on thickness, strength, loads, construction details, soil
moisture, etc., in addition to soil corrosivity, and is, therefore, difficult to predict. Of more practical
value are corrosion control methods that will increase the life of materials that would be subject to
significant corrosion.
Steel Pipe
Abrasive blast underground steel utilities and apply a high quality dielectric coating such as·
extruded polyethylene, a tape coating system, hot applied coal tar enamel, or fusion bonded epoxy.
Bond underground steel pipe with rubber gasketed, mechanical, grooved end, or other
nonconductive type joints for electrical continuity. Electrical continuity is necessary for corrosion
monitoring and cathodic protection.
Electrically insulate each buried steel pipeline from dissimilar metals, cement-mortar coated and
concrete encased steel, and above ground steel pipe to prevent dissimilar metal corrosion cells and
to facilitate the application of cathodic protection.
With the above recommendations in place, we would not anticipate corrosion problems for at least
20 years and probably much longer. Further, cathodic protection can be easily applied in the future,
if necessary.
Hydraulic Elevator
Coat hydraulic elevator cylinders as described above. Electrically insulate each cylinder from
building metals by installing dielectric material between the piston platen and car, insulating the
bolts, and installing an insulated joint in the oil line. Apply cathodic protection to hydraulic
cylinders as per NACE International RP-0169-92. As an alternative to electrical insulation and
cathodic protection, place each cylinder in a plastic easing with a plastic watertight seal at the
bottom.
The elevator oil line should be placed above ground if possible but, if underground, should be
protected as described above for steel utilities.
Iron Pipe
Cast and ductile iron piping do not require special protective measures such as a plastic wrap.
However. to avoid possibly creating corrosion problems, iron should not be placed partially in
contact with concrete such as thrust blocks. Use coatings mentioned above for steel or 8 mil thick
low-density polyethylene or 4 mil thick high-density polyethylene plastic sheets per AWWA C105
to prevent such contact. Electrically insulate underground iron pipe from dissimilar metals and
above ground iron pipe with insulated joints.
LAW/CRANDALL, INC.June 26,1997
MJS&A #97192 Page 4
Copper Tube
No special precautions are necessary for bare copper tubing for cold water. Hot water tubing may
be subject to a higher corrosion rate. The best corrosion control measure would be to place the hot
copper tubing above ground. If buried, encase in plastic pipe to prevent soil contact or apply
cathodic protection.
Plastic and Vitrified Clay Pipe
No special precautions are required for plastic and vitrified clay piping placed underground from a
corrosion viewpoint. Protect any iron valves and fittings with a double polyethylene wrap per
AWWA C105 or as described below for bare steel appurtenances. Where concrete thrust blocks are
to be placed against iron, use a single polyethylene wrap to prevent concrete/iron contact and to
eliminate the slipperiness of a double wrap.
All Pipe
On all pipe, coat bare steel appurtenances such as bolts, joint harnesses, or Dexible couplings with a
coal tar or elastomer based marnie, coal tar epoxy, moldable sealant wax tape, or equivalent after
assembly.
Where metallic pipelines penetrate concrete structures such as building floors or walls, use plastic
sleeves, rubber seals, or other dielectric material to prevent pipe contact with the concrete and
reinforcing steel.
Concrete
Any type of cement and standard concrete cover over reinforcing steel may be used for concrete
structures and pipe in contact with these soils.
Please call if you have any questions.
Respectfully Submitted,
M.J. SCHIFF & ASSOCIATES, INC.
«/t«*1) U./utw *&3V
James T. Keegan
Enc:Table 1
z:\docs-97\971 92.doc
Reviewed by:
- Pall<R.64
Paul R. Smith, P.E.
1,52 -oR,,5*,A C *BACR1043 2 It*C Expg-:30.094}
i \00,-A/ 11V>:,\4:n?os\.1..,»,4
M. J. SCHIFF & ASSOCIATES, INC.
Consulting Corrosion Engineers - Since 1959 1291 North Indian Hill Boulevard
Claremont, California 91711-3897
Phone 909-626-0967
FAX 909-621-1419
E-mail SCHIFFCORR@AOL.COM
Table 1 - Laboratory Tests on Soil Samples Page 1 of 1
Santa Ana Police Department Building, Santa Ana, California
Your #70131-7-0261.0001, MJS&A #97192
June 25,1997
Sample ID B-1 B-2A
@ 3.5'@ 3.5'
silty sandySoil Type
sand Silt
Resistivity Units
as-received ohnn-cnn 23,500 7,700
saturated ohm-cm 4,750 3,500
pH 6.5 6.4
Electrical
Conductivity mS/cm 0.10 0.14
Chemical Analyses
Cations
calcium Ca2+ mg/kg 32 88
magnesium Mg2. mg/kg 12 17
sodium Na" mg/kg 45 175
Anions
carbonate C32- mg/kg ND ND
bicarbonate HCO/- mg/kg 85 281
chloride Cll. mg/kg 32 273
sulfate SO42- mg/kg 108 54
Other Tests
sulfide SZ. qual na na
Redox mv na na
ammonium NH4 ' mg/kg na na
nitrate NOj mg/kg na na
Electrical conductivity in millisiemens/cm and chemical analysis are of a 1:5 soil-to-water extract.
mg/kg = milligrams per kilogram (parts per million) of dry soil.
Redox = oxidation-reduction potential in millivolts
ND = not detected
na = not analyzed
docs97\97192.xls
CORROSION AND CATHODIC PROTECTION ENGINEERING SERVICES
PLANS AND SPECIFICATIONS ' FAILURE ANALYSIS ' EXPERT WITNESS ' CORROSIVITY AND DAMAGE ASSESSMENTS