HomeMy WebLinkAbout159997_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2007 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Please return marked up set of drawings with corrections.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2010 California Building Standards Code with local amendments.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings (647-5839 or 647-5700)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.To assign the right occupancy, submit a letter addressed to the Building Safety Division describing in detail the manufacturing process from material delivery, storage, handling, packaging, and shipping of finish product. Include an equipment list describing use in the process.B occupancy shall be separated from F2 occupancy by a one –hour fire resistive assembly.CBC Section 708.4, Fire partitions shall extend from the top of the foundation or floor/ceiling assembly below to the underside of the floor or roof sheathing, slab or deck above or to the fire-resistance-rated floor/ceiling or roof/ceiling assembly above, and shall be securely attached thereto. If the partitions are not continuous to the sheathing, deck or slab, and where constructed of combustible construction, the space between the ceiling and the sheathing, deck or slab above shall be fire-blocked or draft-stopped in accordance with Sections 717.2 and 717.3 at the partition line. The supporting construction shall be protected to afford the required fire-resistance rating of the wall supported, except for tenant and sleeping unit separation walls and corridor walls in buildings of Types IIB, IIIB, and VB construction. (provide complete detail)CBC Section 708.9, Penetrations in a fire partition by ducts and air transfer openings shall comply with Section 716.All the doors at one hour fire rated walls shall be rated according to table 715.4.Please clarify difference between the walls numbers eg: # 11,12,10,….Show how wall #12 is being supported at the top.Provide cross reference for all partition walls to show how being supported at the top.Provide complying exiting plan for the “reminder” area. Note the use of adjacent units.Provide number of exits required by CBC Sections 1015 and 1016.Table 1019.2 For Buildings With One Exit:Maximum HeightMaximum OccupantsOf Building(Or Dwelling Units)OccupancyAbove Grade PlanePer Floor And Travel Distance
A, B, E, F, M, U1 Story49 occupants and 75’ travel distance
H-2, H-3, L1 Story3 occupants and 25’ travel distance
H-4, H-5, I, R1 Story10 occupants and 75’ travel distance
I-2, I-2.11 Story7 occupants and 50’ travel distance
S1 Story29 occupants and 100’ travel distanceCBC Section 1015.2.1, Where two exits or exit access doorways are required from any portion of the exit access, the exit doors or exit access doorways shall be placed a distance apart equal to not less than one-half of the length of the maximum overall diagonal dimension of the building or area to be served measured in a straight line between exit doors or exit access doorways. Interlocking or scissor stairs shall be counted as one exit stairway.Provide on the drawings a complete door schedule, showing:
- Door sizes (CBC Sections 1008.1.1 and 1133B.2)
- Hardware complying with exiting and disabled accessibility requirements (CBC Sections 1008.1.8 and
1133B.2.5)
- Compliance with limitation of viewport size (CBC Section 715.4.3 Exception 1)
- Fire-rating of door assembly complying with CBC Section 715 Opening Protection
- Note smoke seal (in accordance with CBC Section 715.4.3, required for doors forming part of the one-hour
exit corridor envelope)
- Show compliance with the City of Santa Ana’s Security Ordinance (Contact the Santa Ana Police Department
Crime Prevention Section by telephoning 714-647-5840)The width of the level area on the side to which the door swings shall extend 24” past the strike edge of the door for exterior doors and 18” past the edge for interior doors. CBC Section 1126A.3.2.CBC Section 1011.1. Provide a directional exit sign at changes in exiting direction.This building is subject to the State of California Energy Conservation Regulations:
- The permit applicant shall be responsible for obtaining an energy plan check from a consultant who is
qualified to perform an energy efficiency analysis in accordance with the California Code of Regulations
(CCR,) Title 24, Par 6, 2008 California Energy Code. The plan check consultant must sign documentation
certifying that a thorough, competent review has been performed on behalf of the Enforcement Agency.
- The corrected/final ARCHITECTURAL drawings shall have the required energy efficiency compliance
documentation with completed signature blocks filed on the plans. The same information may be copied on
the Electrical Plans for the Electrical Plan Checker.
- Provide cool roofing as required by 2008 Energy Standards.
- The energy plan check consultant must complete the attached “Energy Conservation Plan Check Consultant
Qualification Statement.”
- Refer to the attached information sheet.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636.The reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)