HomeMy WebLinkAbout159619_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2007 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Please return marked up set of drawings with corrections.Clearly indicate the scope of work under this building permit application:
- Delete all notes and details from drawings that are not a part of the work to be done under the subject building
permit application. This includes mechanical, plumbing and electrical work that is not specifically required by
the Building Code.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings (647-5839 or 647-5700)
- Public Works Agency approval (647-5039)
- County of Orange Health Department approval on the corrected/final set of drawings (667- 3600)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuancePlease fill out attached handicap compliance form.Clarify if the curb ramp is new or existing.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Exit illumination and exit sign requirements in accordance with CBC Section 1011 shall be shown on the drawings. Be specific as to the type of exit signs to be installed.Show sink # 31 is in compliance with H/C accessibility.CBC Sections 1115B and 1210. Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.All dining, banquet, and bar facilities shall be made accessible to persons with disabilities as provided in CBC Section 1104B.5. At least 5%, but not less than one of the seating spaces in each functional area is accessible as follows:
- Provide a minimum 30” x 48” wheelchair clear floor space.
- Provide knee space at tables at least 27” high, 30” wide and 19” deep.
- Provide height of tables between 28” – 34” from the floor ground.
- Provide access to accessible seating space(s) by aisles with a minimum of 36” in width.CBC Section 1110B.1.3, Check Stands CBC Table 11B-2:
NUMBER OF REGULARNUMBER TO BE
CHECKSTANDSACCESSIBLE
1 to 41
5 to 82
9 to 153
Over 153 plus 20% of additional aisles
- In new and existing construction, accessible check stands shall provide a clear checkout aisle width of 36”
with a maximum adjoining counter height not exceeding 38” above the finish floor.
- The top of the counter lip shall not exceed 40” above the finish floor.
- Accessible check stands shall always be open to customers with disabilities and shall be identified by a sign
clearly visible to those in wheelchairs. The sign shall display the international symbol of accessibility in white
on a blue background and shall state “This check stand to be open at all times for customers with disabilities.”Verify if the walk in cooler and walk in freezer is custom or prefabricated.If walk in cooler is prefabricated provide ICC repot number , if it is custom provide construction detail.Detail 4/4 doesn’t match new full height wall.Show location of pony wall on the floor plan.Clarify type of the ceiling on ceiling plan and verify if there is a new ceiling or existing.If there is a new ceiling , see comments 23 – 26.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636.Provide a complete suspended ceiling system plan and section detail showing the following:
- Vertical supports
- Seismic wires
- Seismic strut/Compression strut
- Perimeter wires
- Separate fixture wires for lights and mechanical devices
- ICC Research Report number for the suspended ceilingThe reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)Show location of the Prefab soffit.On the detail clearly show how the prefab soffit is being supported from the structure above.Clarify type the hood.Provide weight of the hood and exhaust fan on the drawings.