HomeMy WebLinkAbout164251_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Please return marked up set of drawings with corrections.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings (647-5839 or 647-5700)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Please fill out attached handicap compliance form.Provide the following:
- Disabled access compliance must be shown on the site plan.Show on the plans:
- Occupancy Classification(s)
- Type of Construction
- Fire Sprinkler System (State purpose of sprinkler system, for example, area increase under CBC Section Occupancies storing, handling, using, and/or selling hazardous materials, liquids, and chemicals shall submit a list of all said materials, listing their quantities and how they relate to specific California Building Code Table items. Note on the Floor Plan, type and quantity of hazardous material in each control area and fire-resistive rating for fire barriers.Submit a letter addressed to the Building Safety Division describing in detail the manufacturing process from material delivery, storage, handling, packaging, and shipping of finish product. Include an equipment list describing use in the process.Provide complete floor plan for both suites A and B.Note on the floor plan type of occupancy for each room.Exit illumination and exit sign requirements in accordance with CBC Section 1011 shall be shown on the drawings. Be specific as to the type of exit signs to be installed.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Provide continuous walking surface from H/C parking to the entrance of each suite.On both section A/A-1 and B/A-2 , provide detail to show stability at the hinges.Provide type 5/8 X gypsum board at both sides on the 1-hr fire rated wall.Provide fire caulking at all the gaps in 1- hr fire rated wall with Icc report number to maintain fire Integrity.