HomeMy WebLinkAbout164270_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2010 California Residential Code (CRC); 2010 California Building Code (CBC); CMC = 2010 California Mechanical Code; CPC = 2010 California Plumbing Code; CEC = 2010 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2010 California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.All persons preparing plans for others shall sign those plans. Business and Professions Code Chapter 3, Division 3, Section 5536.1 (a).
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper.
Provide a statement on the title sheet of the plans that this project shall comply with following codes:
- 2010 California Residential Code (CRC)
- 2010 California Building Code (CBC)
- 2010 California Electrical Code (CEC)
- 2010 California Mechanical Code (CMC)
- 2010 California Plumbing Code (CPC)
- 2010 California Energy Code (CEnC)
- City of Santa Ana Municipal CodeAll new construction, Interior or exterior alterations, repairs, or additions requiring a permit and having a valuation in excess of $1,000,, an approved carbon monoxide alarm shall be installed in dwelling units and in sleeping units within which fuel-burning appliances are installed and in dwelling units that have attached garages shall be provided with carbon monoxide alarms (CRC R315)
- Carbon monoxide alarms shall only be required in the specific dwelling unit or sleeping unit for
which the permit was obtained. Carbon monoxide alarms required by Sections R315.1 and
R315.2 shall be installed in the following locations: ________.
- Outside of each separate dwelling unit sleeping area in the immediate vicinity of the bedroom(s).
- On every level of a dwelling unit including basements.
- Where more than one carbon monoxide alarm is required to be installed within the dwelling unit or
within a sleeping unit the alarm shall be interconnected in a manner that activation of one alarm
shall activate all of the alarms in the individual unit.
Exception:
Interconnection is not required in existing dwelling units where repairs do not result in the removal of wall and ceiling finishes, there is no access by means of attic, basement or crawl space, and no previous method for interconnection existed.Shower compartments and walls above bathtubs with shower heads installed shall be finished with a smooth, nonabsorbent surface to a height of not less than 72” above the floor. (CRC R307.2)Glass enclosure doors and panels must be labeled Category II. Swing door outward. Net area of shower receptor shall be not less than 1,024 sq. in. of floor area, and encompass 30-inch diameter circle. (CPC411.7)
Specify on the framing plans the shear wall material, thickness, size and spacing of fasteners and sole plate nailing. Call out anchor bolt spacing and hold down hardware on foundation plan.
Detail how the interior shearwalls are connected to the roof diaphragm.
Show Radiant Barrier, Cool Roofing, and Duct Ceiling as required by the 2008 California Energy Residential Manual for prescriptive Package D.
The walls on roof framing plan are not clear, on roof framing plan verify new and existing walls.
Verify if the removed interior wall is bearing wall or not.
Provide beam at the new opening on the roof framing plan.
Provide shear wall on four sides of the addition.
Provide detail for post installed anchor bolts.