HomeMy WebLinkAbout168473_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Clearly indicate the scope of work under this building permit application:
- Revise project job description on the building permit application worksheet to reflect the work to be done
under the subject building permit application.
- Clarify “reworking of existing lobby floor” and “new sloped floors” in the project scope. The plans do not show this work.
- Revise the sliding door description and the storage room listed is not show on plans.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings (647-5839 or 647-5700)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceCBC Section 1008.1.8, Note on drawing: “Exit doors shall be openable from the inside without the use of a key or any special knowledge or effort.”The width of the level area on the side to which the door swings shall extend 24” past the strike edge of the door for exterior doors and 18” past the edge for interior doors. CBC Section 1126A.3.2.The floor or landing at each side of an exit door shall be level and having a length in the direction of the door swing of at least 60” and the length opposite the direction of door swing of 44” as measured at right angles to the plane of the door in the closed position. CBC Section 1126A.3.1.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.If applicable: Any accessible route of travel shall be considered a ramp if its slope is greater than 1’ rise in 20’ of horizontal run (5-percent gradient) and show compliance with CBC Sections 1010 and 1133B.5.1.
- Pedestrian ramps used as exits shall show compliance with CBC Sections 1010 and 1133B.5.
- Provide complete architectural plan views, sections, details, and notes for pedestrian ramps.
- An aisle ramp slope in occupancies of Group A shall comply with Section 1025.11.
- CBC Sections 1010.3 and 1133B.5.3.1. The slope measured perpendicular to the direction of travelof a ramp
shall not be steeper than one unit vertical in 48 units horizontal (2-percent slope).
- CBC Sections 1010.4 and 1133B.5.3. The rise for any ramp run shall be 30” maximum.
- Refer to the attached pedestrian ramp handout.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsValuation of proposed project is calculated as $____________. A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in the immediate previous item as noted in CBC Section 1134B. Revise the drawings to show compliance. Show both existing elements and how they will be upgraded to current standards.Sanitary facilities serving the area of new work shall be disabled accessible. Revise the drawings to show compliance with CBC Section1115B or provide justification for use of existing second floor restrooms for newly created tenant space.Provide completed disabled compliance form (attached).CBC Section 1122B.1. Where a single counter contains more than one transaction station, such as (but not limited to) a bank counter with multiple teller windows or a retail sales counter with multiple cash register stations, at least 5 percent, but never less than one, of each type of station shall be located at a section of counter that is at least 36” long and no more than 28 to 34” high.