HomeMy WebLinkAbout170246_2_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Please return marked up set of drawings with corrections.All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. This requirement applies to both exempt and non-exempt projects. Business and Professions Code Chapter 3, Division 3, Section 5536.1(a).This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings (647-5839 or 647-5700)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Please fill out attached handicap compliance form.Provide the following:
- Disabled access compliance must be shown on the site plan.Show on the plans:
- Occupancy Classification(s)
- Type of ConstructionWhen there has been a change in use or occupancy classifications, drawings shall show compliance with the CBC requirements for the new classifications. Reference CBC Section 3406.Identify new walls and new doors on the drawings.Show working area on the site plan with regard to the entire bldg.Provide complying exiting plan for the “remainder” area. CBC Section 1007.2, Continuity and components. Each required accessible means of egress shall be continuous to a public way and shall consist of one or more of the following components: Accessible Routes, Stairways, Elevators, Horizontal Exits, Ramps, or Areas of Refuge.Provide number of exits required by CBC Sections 1015 and 1016.CBC Section 1016.1. Travel distance limitations. Exits shall be so located on each story such that the maximum length of exit access travel, measured from the most remote point within a story to the entrance to an exit along the natural and unobstructed path of egress travel, shall not exceed the distances given in Table 1016.1.(for the remainder area)Provide on the drawings a complete door schedule, showing:
- Hardware complying with exiting and disabled accessibility requirements (CBC Sections 1008.1.8 and
1133B.2.5)CBC Section 1008.1.2, Exit doors shall swing in the direction of exit travel when serving any hazardous area or when serving an occupant load of 50 or more.Show landing at the exit doors. Panic hardware shall comply with CBC Section 1008.1.9. Panic hardware shall be provided as required by CBC Section(s):
- An Occupancy with an occupant count > 50. Refer to CBC section 1008.1.8.3, Item 2 for Exception.
- I-2 or I-2.1 Occupancy with an occupant count > 50
- Electrical rooms with equipment rated 1,200 amperes or more and over 6’ wide that contain over current
devices, switching devices or control devices with exit access doors shall be equipped with panic hardware
and doors shall swing in the direction of egress.
- By the Fire Department Provide specifications for doors hardware (i.e., lever type, push-pull panic, etc) to comply with disabled access requirements. CBC Section 1133B.2.5.2.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Provide minimum 18” clearance to the strike edge of the door marked on the plan.Provide minimum 36” opening at the reception desk.Show handicap portion of reception desk is minimum 36” wide.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Show how shelves between 6’-8’ high will be anchored.Show how left side suite has an access to the bathroom.Clarify if there is any ceiling alteration.