PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2010 California Residential Code (CRC); 2010 California Building Code (CBC); CMC = 2010 California Mechanical Code; CPC = 2010 California Plumbing Code; CEC = 2010 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper. Glazing in door and enclosures for hot tubs, whirlpools, saunas, steam rooms, bathrooms, showers less than 5’ above the standing surface shall have a minimum category classification of II (CPSC 16 CFR 1201). (CRC TR308.3.1 (1) & 308.4(5)) Show maximum 44 inch sill height for window in bedroom # 3in Provide a complete full-height section and details of stairway showing: (CRC R311.7)
- Minimum headroom of 6 feet 8 inches. Show head clearance at the front porch. 3”x3”x.229” steel plate washers are required on all anchor bolts in a braced wall line. (CRC R403.1.6.1)
Detail how the interior shear walls are connected to the roof/floor diaphragm(s). (1603)
Change 4 x 6 header between bedroom and bathroom to 4x8 since there are load from ridge beam.
Change 4 x 4 header at the walk in closet to 4 x6 for additional load from ceiling joists.
Justify how existing hip will carry additional load from the California framing
The City has encountered a large number of inspection problems arising from a lack of specific framing details. The following listed items are required to be shown on the plans (CBC 107.1):
- All plumbing walls are to be framed with a minimum of 6" studs.
- Permissible notching and boring of joists are to be shown on the plans and shall not exceed CBC
Section 2308.10.4.2 allowances.
- Notching of exterior and bearing/nonbearing walls shall not exceed 25%/40% respectively. Bored
holes in bearing/nonbearing walls shall not exceed 40%/60% respectively. In no case shall the
edge of the bored hole be nearer than 5/8 inch to the edge of the stud. (2308.9.10 and 2308.9.11)
Provide details for retrofit shear and tension anchor bolts on plans. Provide calculations as needed.
Note on the drawings “ Special inspection for Simpson epoxy is required.”
Santa-ana is under climate zone 8, please revise CF-1R form accordingly.Revise framing plans to provide a radiant barrier at roof for Climate Zones 8 when using the prescriptive approach. (2008 CESC 151(f) 2)