REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Please return marked up set of drawings with corrections.CBC Section 107.3.4, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings (647-5839 or 647-5700)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceIf applicable: Occupancies storing, handling, using, and/or selling hazardous materials, liquids, and chemicals shall submit a list of all said materials, listing their quantities and how they relate to specific California Building Code Table items. Note on the Floor Plan, type and quantity of hazardous material in each control area and fire-resistive rating for fire barriers.If applicable: Occupancies using hazardous materials are subject to special requirements. It is the applicant’s/owner’s responsibility, PRIOR TO SUBMITTAL, to make this known to the Building, Planning, or Fire Departments.Provide completely dimensioned floor plans.Provide typical section view detail of all new partitions and ceilings showing:
- Size, spacing, and material of framing members
- Note gauge and ICC Research Report number and installation/construction requirements for metal framing
members.
- Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13
for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations
and drawing prepared by a registered engineer are submitted for review. Submit structural engineering
calculations for walls in rooms with a floor to building structure above height greater than 14’.
- Provide on the drawings details for the lateral support of partitions, rails and similar space dividers less than
5’ 9” in height.
- Sheathing material and details of attachment. Note type, size, and spacing of fasteners.
- Heights of partition, suspended ceiling, structure above.
- Reference each fire-resistive assembly to a CBC Chapter 7 Table and Item number.
- Fire-blocks and draft-stops in combustible construction in accordance with CBC Section 717. Show
location(s) and provide typical construction details.The length of a common path of egress travel in Group B, F and S occupancies shall not be more than 100’, provided that the building is equipped throughout with an automatic sprinkler system installed. CBC Section 1014.3.Revise common path of egress dashed line for the break room on exit plan Sheet A-0.5. Path of egress shall go from office area to warehouse or manufacturing area.Shown common path of egress from left side of office area exceeds 100 feet. Please verify.Common path of egress for the mezzanine exceeds 100 feet. The common path includes distance to exit at the first floor due to only one exit at first floor office area. Both existing stairways are required exits. Provide exit signage for both exits and provide additional exit signs at the first floor to nearest exits.
Revise occupancy type to S-1 for the warehouse or provide substantiation that the use will be less hazardous. Also note that S-2 occupancy requires a rated occupancy separation from the B and F-1 occupancies per Table 508.4.
Siteplan Sheet A-0.4: Verify and show all exit doors to have clear path of egress with landings where parking spaces do not occur. Provide bollards where adjacent parking spaces my block egress.
Clarify and callout if maintenance area at rear is new or existing. If new, provide complete construction details.
Revise exit sign location left side of new office area. Egress from the office shall not enter the warehouse area.
CBC Section 1011. Provide a directional exit sign at changes in exiting direction.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of a stairway or ramp shall be
identified by a tactile exit sign with the following words as appropriate:“EXIT STAIR DOWN”“EXIT RAMP DOWN”“EXIT STAIR UP”“EXIT RAMP UP”It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsPriority shall be given to those elements that will provide the greatest access in the above order.Valuation of proposed project is calculated as $____________. A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in the immediate previous item as noted in CBC Section 1134B. Revise the drawings to show compliance. Show both existing elements and how they will be upgraded to current standards.Provide a completed Disabled Access Compliance Form (see attached).CBC Section 1007.1, Accessible spaces shall be provided with not less than one accessible means of egress. Where more than one means of egress is required by Section 1015.1 or 1019.1 from any accessible space, each accessible portion of the space shall be served by accessible means of egress in at least the same number as required by Section 1015.1 or 1019.1, Chapter 11A or 11B, as applicable.This building is subject to the State of California Energy Conservation Regulations:
- The permit applicant shall be responsible for obtaining an energy plan check from a consultant who is
qualified to perform an energy efficiency analysis in accordance with the California Code of Regulations
(CCR,) Title 24, Par 6, 2010 California Energy Code. The plan check consultant must sign documentation
certifying that a thorough, competent review has been performed on behalf of the Enforcement Agency.
- The corrected/final ARCHITECTURAL drawings shall have the required energy efficiency compliance
documentation (ENV forms) with completed signature blocks filed on the plans.
- The energy plan check consultant must complete the attached “T24 Review Form.”