PLAN CHECK NO:
PROJECT ADDRESS:
PLAN CHECK ENGINEER:TEL:714FAX:714
647-5897
TYPE OF CONSTRUCTION:
OCCUPANCY CLASSIFICATION(S):
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Please return marked up set of drawings with corrections.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuancePlease fill out attached handicap compliance form.Submit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Submit a letter addressed to the Building Safety Division describing in detail the manufacturing process from material delivery, storage, handling, packaging, and shipping of finish product. Include an equipment list describing use in the process.Show square foot for the entire building. (to assign the right occupancy)Table 1016.1 Exit Access Travel Distance:
OCCUPANCYWITHOUT SPRINKLERWITH SPRINKLERSYSTEM (feet)SYSTEM (feet)
A, E, F-1, I-1, M, R, S-1200250b
B200300c
F-2, S-2, U300400cTable 1019.2 For Buildings With One Exit:Maximum HeightMaximum OccupantsOf Building(Or Dwelling Units)OccupancyAbove Grade PlanePer Floor And Travel Distance
A, B, E, F, M, U1 Story49 occupants and 75’ travel distance
I-2, I-2.11 Story7 occupants and 50’ travel distance
S1 Story29 occupants and 100’ travel distance
B, F, M, S2 Stories30 occupants and 75’ travel distance
R-22 Stories4 dwelling units and 50’ travel distanceProvide ICC report for the new walk in cooler.Show the threshold for walk in cooler is in compliance with handicap accessibility.Identify all the equipments on the floor plan.CBC Section 1011.1. Provide a directional exit sign at changes in exiting direction.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”For the purpose of Section 1011.3, the term “tactile exit signs” shall mean those required signs that comply with Section 1117B.5.1, Item 1.Valuation of proposed project is calculated as $____________. A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in the immediate previous item as noted in CBC Section 1134B. Revise the drawings to show compliance. Show both existing elements and how they will be upgraded to current standards.CBC Section 1607.7. Provide complete grab bar details on the drawings showing compliance with CBC Section 1115B.8 including structural strength to support a 250 pound point load.Show/note ventilation requirements on the plans in accordance with the CBC and California Mechanical Code (CMC) requirements for each type of use.
Note on drawings:
- All enclosed portions of buildings customarily occupied by human beings shall be provided with natural
ventilation by means of openable exterior openings readily controllable by building occupants, with an area not
less than 4% of the floor area being ventilated. CBC Section 1203 and 2010 California Mechanical Code
Section 402.
- Provide mechanical ventilation for each area/room in accordance with the 2010 California Mechanical Code.Show/note LIGHTING requirements on the plans in accordance with CBC and California Electrical Code requirements for each type of use.
Note on drawings:
- CBC Section 1205.2, Natural light. The minimum net glazed area shall not be less than 8 percent of the floor
area of the room served.Note on drawings:
- CBC Section 1205.3, Artificial light. Artificial light shall be provided that is adequate to provide an average
illumination of 10’candles (107 lux) over the area of the room at a height of 30”above the floor level.Show height of the partition walls on detail 3/ A2.1.On detail 2/A2.1 show how the hinge will be prevented.Provide span table for the metal studs.Door # 14 showed as existing , please verify the new framing members on detail 4/ A2.1.Show door # 14 is in compliance with H/C accessibility.Verify if t-bar ceiling will be used in the bathroom.Show how detail 9/ A2.1 is being supported laterally.Show all the sinks are in compliance with H/c accessibility.Provide exit plan.Is there any roof top unit for walk in cooler? If there is provide engineering calculation and detail.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636. (Or please see comments 21-23)Provide a complete suspended ceiling system plan and section detail showing the following:
- Vertical supports
- Seismic wires
- Seismic strut/Compression strut
- Perimeter wires
- Separate fixture wires for lights and mechanical devices
- ICC Research Report number for the suspended ceilingThe reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)