PLAN CHECK NO:
10177737
PROJECT ADDRESS:
1330 S Auto Mall Dr
PLAN CHECK ENGINEER:
Vo, TungTEL:714
647-5830FAX:714
647-5897
TYPE OF CONSTRUCTION:
II B
OCCUPANCY CLASSIFICATION(S):
U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
12/3/2012
INITIAL REVIEW
12/18/2012
EXPIRATION
6/1/2013
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Carl Chrisman
3.
TEL:
(760)729-0533
FAX:
VALUATION:$72,650.00
EMAIL:
cchrisman@wagnerarchitecture.com
FLOOD ZONE:X-0602320277J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.Please return marked up set of drawings with corrections.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2010 California Building Standards Code with local amendments.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.Note on the drawings and submit a copy of ICC Research Report for: Metal Deck.