HomeMy WebLinkAbout185355_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10178550
PROJECT ADDRESS:
1218 E Seventeenth St
PLAN CHECK ENGINEER:
Vo, TungTEL:714
647-5830FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/17/2013
INITIAL REVIEW
5/16/2013
EXPIRATION
10/14/2013
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Andrew Ma
3.
TEL:
(626)202-3648
FAX:
VALUATION:$51,337.00
EMAIL:
ama9292@yahoo.com
FLOOD ZONE:X-0602320163J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.Please return marked up set of drawings with corrections.Clearly indicate the scope of work under this building permit application:
- Revise project job description on the building permit application worksheet to reflect the work to be done
under the subject building permit application.
- Construction drawings must clearly show all work to be done under the subject building permit application.
- Delete all notes and details from drawings that are not a part of the work to be done under the subject building
permit application. This includes mechanical, plumbing and electrical work that is not specifically required by
the Building Code.All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. This requirement applies to both exempt and non-exempt projects. Business and Professions Code Chapter 3, Division 3, Section 5536.1(a).The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceCBC Section 1127B.3, All building entrances that are accessible to and usable by persons with disabilities shall be identified with a least one standard sign and with an additional directional signs, as required, to be visible to persons along approaching pedestrian ways.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”Provide completely dimensioned floor plans, elevations and sections of sanitary facility insuring wheelchair clearances complying with CBC Section 1115B and the California Plumbing Code.CBC Sections 1115B and 1210. Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.CBC Section 1115B.4.3 Item 4. Note on the drawings hot water and drain pipes under lavatory shall be insulated.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636.Provide a complete suspended ceiling system plan and section detail showing the following:
- Vertical supports
- Seismic wires
- Seismic strut/Compression strut
- Perimeter wires
- Separate fixture wires for lights and mechanical devices
- ICC Research Report number for the suspended ceilingNote ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)
Correction is ready to pick up at the counter. Please see additional corrections on plan and calculation. Additional corrections may follow when revised plan resubmitted.