PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10179067
PROJECT ADDRESS:
2101 E Fourth St Unit# 200 Bldg# B
PLAN CHECK ENGINEER:
Kwak, JasonTEL:714
647-5866FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/19/2013
INITIAL REVIEW
7/18/2013
EXPIRATION
12/16/2013
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Jill Buckley
3.
TEL:
(949)679-6456
FAX:
VALUATION:$428,251.00
EMAIL:
jill@cdlassociatesinc.com
FLOOD ZONE:X-0602320277J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5866 for an appointment.Clearly indicate the scope of work under this building permit application:
- Revise project job description on the building permit application worksheet to reflect the work to be done
under the subject building permit application.
- Include structural upgrade to floor framing for the storage areas and new moveable partition.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide notes on plans that corridors will not be created by partitions. Callout maximum 5’-9” height or the following requirement for corridors will apply. (Comments 9 thru 13)Label and note hourly fire rating of:
- All corridors (if applicable)Reference each fire-resistive assembly to a CBC Chapter 7, Table and Item number:
(if applicable for rated corridor)- Walls
- Ceilings
- Columns
- CorridorsCorridors shall be fire-resistance rated in accordance with Table 1017.1. The corridor walls required to be fire-resistance rated shall comply with Section 708 for fire partitions.CBC Section 1017.2, Corridor width. The minimum corridor width shall be as determined in Section 1005.1, but not less than 44”.Provide typical complete section view through one-hour corridor(s) showing compliance with CBC Sections 1017 and 708:
- Size, spacing, and material of framing members. Note gauge and ICC number and installation/construction
requirements for metal framing members.
- Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13
for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations
and drawings prepared by a registered engineer are submitted for review. Submit structural engineering
calculations for walls in rooms with a floor to building structure above height greater than 14’.
- Sheathing material and details of attachment. Note type, size, and spacing of fasteners.
- Height of partition, suspended ceiling, structure above.
- Reference each wall and ceiling fire-resistive assembly to a CBC Chapter 7 Table and item number.
- Fire blocks and draft stops in combustible construction in accordance with CBC Section 717. Show
location(s) and provide typical construction details.
- Fire/smoke damper locations, installation requirements, and required access doors. Refer to CBC Section
716 and Mechanical Code Section 606.The floor or landing at each side of an exit door shall be level and having a length in the direction of the door swing of at least 60” and the length opposite the direction of door swing of 44” as measured at right angles to the plane of the door in the closed position. See landing at existing stairway on west side.Modifications to the stairway and handrail cannot be done under a separate permit. Provide compliance to current disabled accessible requirements.Stairways shall show compliance with CBC Sections 1009 and 1133B.4 including applicable disabled accessibility requirements.
- Provide complete architectural plan view, sections, details, and notes for stairway(s).
- Dimension stairway width showing compliance with CBC Sections 1009.1, 1005, and 1007.3.
- Dimension rise of steps shall be not less than 4” or greater than 7”. The run shall notbe less than 11”.
- Treads, nosing, and risers require compliance with CBC Section 1133B.4.5, including no open risers and slip
resistant treads.
- CBC Section 1009.2, Dimension stairway headroom clearance. 6’ 8” minimum clearance.
- Refer to the attached stairway handout; show compliance on the drawings.Provide handrail details on the drawings showing compliance with CBC Section 1009.10, 1012, and 1133B.4.1.
- Stairways shall have handrails on each side.
- Every stairway required to be more than 88” in width shall be provided with not less than one intermediate
handrail for each 88” of required width. Intermediate handrails shall be spaced approximately equally across
with the entire width of the stairway.
- Handrails shall be 34 to 38” above the nosing of treads.
- Handrails shall extend a minimum of 12” beyond the top nosing, and shall extend a minimum of 12” plus the
tread width beyond the bottom nosing.
- Ends of handrails shall be returned or shall terminate in newel posts of safety terminals.
- Handrails projecting from a wall shall have a space of 1½” between the wall and the handrail.
- The handgrip potion of handrails shall not be less than 1¼” nor more than 1½” cross-sectional dimension or
the shape shall provide an equivalent gripping surface. The handgrip portion of handrails shall have a smooth
surface with no sharp corners. Any wall or other surface adjacent to the handrail shall be free of sharp or
abrasive elements. Edges shall have a minimum radius of 1/8”.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsCBC Section 1114B.1.2, 1114B.1.3. and 1129B.3, Item 3. Entrance(s) to the building or facility and primary path of travel to the specific area of new work, alteration, structural repair or addition shall be accessible. Path of travel incorporated all elements from the exterior arrival site to remodeled area.CBC Section 1129B.3, Item 3. Parking spaces must be located so that the disabled are not compelled to walk or wheel behind parked cars other than their own.Clarify path of travel shown to be on vehicular way instead of existing sidewalk.Plumbing facilities shall be provided in accordance with the California Plumbing Code (CPC) Section 412.0 and CPC Table 4-1. Provide plumbing fixture calculations.Note type of safety glazing complying with CBC Section 2406 for hazardous locations listed under CBC Section 2406.3.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636.Suspended drywall ceiling requires structural engineering. The provided structural plans only list hard lid framing at restrooms.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)