APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.Please return marked up set of drawings with corrections.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Orange County Fire Authority approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by
the Public Works Agency (647-5039)
- School District Compliance Certificate; a copy of the building permit application, signed by the plan check
engineer, shall be required by the School District to verify the scope of work. Refer to the attached handout.
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceA separate Building Permit Application is required for:
- Storage RacksProvide pedestrian protection in accordance with CBC Section 3306. Show location and type of protection on plan view. Provide typical construction details, sections, and elevations of pedestrian protection required. Pedestrian protection constructed within a public right of way shall require a building permit issued by the Building Safety Division and a separate approval from the City’s Public Works Agency (714) 647-5039.Provide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.
- Provide a fully dimensioned site plan on a separate 8½” x 11” sheet of paper.
- Show all property lines of record on the site plan. Show compliance with CBC Section 704 and CBC Tables
601, 602, and 704.8.Occupancies storing, handling, using, and/or selling hazardous materials, liquids, and chemicals shall submit a list of all said materials, listing their quantities and how they relate to specific California Building Code Table items. Note on the Floor Plan, type and quantity of hazardous material in each control area and fire-resistive rating for fire barriers. Provide fire blocking in concealed spaces of stud walls and partitions, including furred spaces at the ceiling and at 10 ft. intervals.Fireblocking. In combustible construction, fireblocking shall be installed to cut off concealed draft openings (both vertical and horizontal) and shall form an effective barrier between floors, between a top story and a roof or attic space. Fireblocking shall be installed in the locations specified in CBC Sections 717.2.2 through 717.2.7.Provide complete details on the drawings showing compliance with CBC Section 1405 requirements for veneer construction.CBC Section 1127B.1. Site development shall be designed to provide access to all entrances and exterior ground-floor exits and access to normal paths of travel; and where necessary, to provide access shall incorporate pedestrian ramps, curb ramps, etc.CBC Sections 1133B.7.1 and 1133B.7.5. Sidewalks accommodating the disabled must be at least forty-eight inches (48”) wide and at least sixty inches (60”) where door swings over walk.CBC Sections 1102B, 1124B.1 and 1127B.1. Provide a continuous walking surface from each exit door to public way.If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 1133B.8.5.
Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC Section 1133B.8.5.CBC Section 1129B.1. Accessible parking spaces serving a particular building shall be located on the shortest accessible route of travel from adjacent parking to an accessible entrance. Provide parking data on the site plan showing the total number of parking spaces provided, the number of disabled accessible spaces and the number of van accessible spaces, showing compliance with CBC Section 1129B and CBC Table 11B-6.CBC Section 1129B.3, Item 3. Parking spaces must be located so that the disabled are not compelled to walk or wheel behind parked cars other than their own.CBC Section 1129B.3, Item 4. Surface slopes of accessible parking spaces shall be the minimum possible and shall not exceed 1 unit vertical to 50 units horizontal (2% slope) in any direction.CBC Section 1129B.3, Item 2. One in every eight accessible spaces, but not less than one, shall be served by an access aisle 8’-0” (96”) wide minimum and shall be designated van accessible as required by Section 1129B.4. The words NO PARKING shall be painted on the ground within each eight’ loading and unloading access aisle. This notice shall be painted in white letters no less than 12” high and located so that it is visible to traffic enforcement officials. See Figure 11B-18B.CBC Section 1122B.1. Where a single counter contains more than one transaction station, such as (but not limited to) a bank counter with multiple teller windows or a retail sales counter with multiple cash register stations, at least 5 percent, but never less than one, of each type of station shall be located at a section of counter that is at least 36” long and no more than 28 to 34” high.CBC Section 1110B.1.3, Check Stands CBC Table 11B-2:
NUMBER OF REGULARNUMBER TO BE
CHECKSTANDSACCESSIBLE
1 to 41
5 to 82
9 to 153
Over 153 plus 20% of additional aisles
- In new and existing construction, accessible check stands shall provide a clear checkout aisle width of 36”
with a maximum adjoining counter height not exceeding 38” above the finish floor.
- The top of the counter lip shall not exceed 40” above the finish floor.
- Accessible check stands shall always be open to customers with disabilities and shall be identified by a sign
clearly visible to those in wheelchairs. The sign shall display the international symbol of accessibility in white
on a blue background and shall state “This check stand to be open at all times for customers with disabilities.”This building is subject to the State of California Energy Conservation Regulations:
- The permit applicant shall be responsible for obtaining an energy plan check from a consultant who is
qualified to perform an energy efficiency analysis in accordance with the California Code of Regulations
(CCR,) Title 24, Par 6, 2010 California Energy Code. The plan check consultant must sign documentation
certifying that a thorough, competent review has been performed on behalf of the Enforcement Agency.
- The corrected/final ARCHITECTURAL drawings shall have the required energy efficiency compliance
documentation with completed signature blocks filed on the plans. The same information may be copied on
the Electrical Plans for the Electrical Plan Checker.
- Provide cool roofing as required by 2008 Energy Standards.
- The energy plan check consultant must complete the attached “Energy Conservation Plan Check Consultant
Qualification Statement.”A note shall be added to the plan to read: A soils compaction report shall be prepared under direction of the soils engineer, signed and stamped by the soils engineer and be submitted to the Building Safety Division of City of Santa Ana for review and approval prior to foundation inspection.Provide Calc for awning and show its attachment to the wall.See red marks on the following sheets of plan: A0, A-1, A-4, A-6,S0.1, S0.2, S2.1, S2.2, S3.1, S5.1, S8.1, & C4.0