HomeMy WebLinkAbout188720_1_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10179601 PROJECT ADDRESS: 301 N Spurgeon St PLAN CHECK ENGINEER: Heidari, FredTEL:714 647-5862FAX:714 647-5897 TYPE OF CONSTRUCTION: V B, SPK OCCUPANCY CLASSIFICATION(S): A-2 PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 9/5/2013 INITIAL REVIEW 12/9/2013 EXPIRATION 3/4/2014 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Brian Scott 3. TEL: (562)964-1272 FAX: (562)403-1505 VALUATION:$105,900.00 EMAIL: plansbybrian@aol.com FLOOD ZONE:X-0602320276J APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.Please return marked up set of drawings with corrections.All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. This requirement applies to both exempt and non-exempt projects. Business and Professions Code Chapter 3, Division 3, Section 5536.1(a).This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Fire Department approval on the corrected/final sets of drawings ((714)573-6100) - Police Department approval on the corrected/final set of drawings (647-5840) - Public Works Agency approval (647-5039) - County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000) - Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceWhen there has been a change in use or occupancy classifications, drawings shall show compliance with the CBC requirements for the new classifications. Reference CBC Section 3406.Reference each fire-resistive assembly to a CBC Chapter 7, Table and Item number: - Floor/ Ceilings between first floor and the second floor Please see Table 508.4 of CBC 2010. - Columns - Shafts - Provide typical section view detail of all new partitions and ceilings showing: - Size, spacing, and material of framing members - Note gauge and ICC Research Report number and installation/construction requirements for metal framing members. - It is the project designer’s responsibility to coordinate work with the various trades to ensure that the size of the wall cavity will be large enough to accommodate piping, fittings, ducts, etc. There has been a continuing field problem of 2½” wide metal studs not being able to accommodate plumbing pipes. - Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13 for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations and drawing prepared by a registered engineer are submitted for review. Submit structural engineering calculations for walls in rooms with a floor to building structure above height greater than 14’. - Provide on the drawings details for the lateral support of partitions, rails and similar space dividers less than 5’ 9” in height. - Sheathing material and details of attachment. Note type, size, and spacing of fasteners. - Heights of partition, suspended ceiling, structure above. - Reference each fire-resistive assembly to a CBC Chapter 7 Table and Item number. - Fire-blocks and draft-stops in combustible construction in accordance with CBC Section 717. Show location(s) and provide typical construction details. - Fire/smoke damper locations, installation requirements and required access doors. Refer to CBC Section 716 and mechanical Code Section 606.Provide on the drawings interior wall and ceiling finish schedule showing compliance with CBC Section 803 and CBC Table 803.5.Provide complete details on the drawings showing compliance with CBC Section 1405 requirements for veneer construction.CBC Section 1004.3, Posting of occupant load. Every room or space that is assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent.CBC Section 1027.6 Exiting from any occupied point in a building or structure on the subject site must be continuous, unobstructed to a public way. This includes gates which must show compliance with CDB Section 1008.2. Revise drawings to show compliance for the gate at East side.Panic hardware shall comply with CBC Section 1008.1.10. Panic hardware shall be provided as required by CBC Section(s): - An Occupancy with an occupant count > 50. Refer to CBC section 1008.1.10 for the gate on the West sideAll doors require a level floor landing on each side in accordance with CBC Sections 1008.1.4, 1008.1.5, 1008.1.6, and 1133B.2.4 and CBC Figures 11B-26A and 11B-26B. Provide typical door threshold details and details of change in floor covering material.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. Please update the note #2 under Exit requirements on sheet A-0.1 of drawing.CBC Section 1127B.3, All building entrances that are accessible to and usable by persons with disabilities shall be identified with a least one standard sign and with an additional directional signs, as required, to be visible to persons along approaching pedestrian ways.CBC Section 1006, Requires means of egress from all occupied parts of the building be provided with at least 1’ candle of light at floor level. Show compliance on the drawings.Provide completely dimensioned floor plans, elevations and sections of sanitary facility insuring wheelchair clearances complying with CBC Section 1115B and the California Plumbing Code. See redmarks on sheet A-3.2 of drawingsCBC Sections 1115B and 1210. Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.CBC Section 1115B.4.3 Item 4. Note on the drawings hot water and drain pipes under lavatory shall be insulated.All dining, banquet, and bar facilities shall be made accessible to persons with disabilities as provided in CBC Section 1104B.5. At least 5%, but not less than one of the seating spaces in each functional area is accessible as follows: - Provide a minimum 30” x 48” wheelchair clear floor space. - Provide knee space at tables at least 27” high, 30” wide and 19” deep. - Provide height of tables between 28” – 34” from the floor ground. - Provide access to accessible seating space(s) by aisles with a minimum of 36” in width.Counters where food or drink is served shall show compliance with the following: - Top of counter is between 28” – 34” above the finish floor. - Knee clearance to be a minimum 27” high, 30” wide, and 19” deep. Exception: Knee clearance is not required at checkout counters or service counters. - Clear floor space a minimum of 30” by 48”. - Clear floor space adjoins an accessible route.Note type of safety glazing complying with CBC Section 2406 for glazing in fixed or operable panels adjacent to a door where the nearest exposed edge of the glazing is within a 24” arc of either vertical edge of the door in a closed position and where the bottom exposed edge of the glazing is less than 60” above the walking surface.Provide structural calculations and drawings, stamped and signed by a California licensed architect or registered civil engineer for: - New mechanical equipment on roof (note on Roof Framing Plan weight of each existing and new piece of equipment on the roof) - New equipment screening on roof - Structural support of shaft(s) and hood(s) - Any other structural alteration - Removal or alteration of existing shear wallsSee red marks on the following sheets of drawing:A-0.1,A-0.3, A-3.0, A-3.1, A-3.2, A-3.4, A-5.0, and A-9.2