REMARKS/RECHECK ITEMS:
APPLICATION
INITIAL REVIEW
EXPIRATION
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
3.
TEL:
FAX:
VALUATION:
EMAIL:
FLOOD ZONE:
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2010 California Residential Code (CRC); 2010 California Building Code (CBC); CMC = 2010 California Mechanical Code; CPC = 2010 California Plumbing Code; CEC = 2010 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
All drawings and supporting documents shall be prepared, stamped, and signed by a California licensed architect or registered professional engineer. (CRC R301.1.3, CBC 107.1 and 107.3.4.1).
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Delete notes and details that do not apply to this project. (CBC 107)
Provide an Index of drawings on cover sheet.Provide complete project description with detailed description of scope of work.Shower compartments and walls above bathtubs with shower heads installed shall be finished with a smooth, nonabsorbent surface to a height of not less than 72” above the floor. (CRC R307.2)Bathrooms, laundry rooms, water closet compartments and similar rooms shall be mechanically ventilated in accordance with the CMC.Specify a minimum 0.019” (No. 26 galvanized sheet gage) corrosion-resistant or plastic weep screed located below foundation plate line and 4 inches above grade on all exterior stud walls or 2-inches above paved areas. (CRC R703.6.2.1)
Submit engineering calculations for vertical and lateral loads prepared by a registered Civil, Structural Engineer or Architect. Additional Structural Corrections may apply.
Provide a minimum of two No. 4 bars at top and at bottom of continuous footing.
Structural framing not using Conventional Light-Frame Construction Provisions of CRC requires the plans and calculations to be signed and sealed by an architect or civil/structural engineer. (CBC 107.3.4)
Cross reference all calculations for joists, beams, shear walls, etc., to framing/floor plans.
Clearly identify all design assumptions & load criteria on the plans. As a minimum:
- Dead Loads of roof/ceiling, floors, exterior/interior walls (R301.2.2.2.1);
- Live Loads for roof, attics with limited storage, attics without storage, habitable attics and attics
served with fixed stairs, floors, and balconies/decks, and stairs per Tables R301.5 & R301.6;
- Wind Loads per Section R301.2.1and wind exposures per Section R301.2.1.5;
- Seismic Loads per Section R301.2.2;
- Local Jurisdiction Design Criteria per Table R301.2(1)