PLAN CHECK NO:
10180083
PROJECT ADDRESS:
2403 W Pomona St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/7/2013
INITIAL REVIEW
11/12/2013
EXPIRATION
5/6/2014
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Lane Curtis
3.
TEL:
(714)381-8393
FAX:
VALUATION: $24,634.00
EMAIL:
lane.curtis@gmail.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2010 California Residential Code (CRC); 2010 California Building Code (CBC); CMC = 2010 California Mechanical Code; CPC = 2010 California Plumbing Code; CEC = 2010 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
All drawings and supporting documents shall be prepared, stamped, and signed by a California licensed architect or registered professional engineer. (CRC R301.1.3, CBC 107.1 and 107.3.4.1).All persons preparing plans for others shall sign those plans. Business and Professions Code Chapter 3, Division 3, Section 5536.1 (a).
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper.
Provide building information on plans:
- Occupancy type: R3 / U
- Construction type: Type V – B
Show North arrow on plan views.
Provide eave / overhang / projection setback to all property lines.Basements, habitable attics, and every sleeping room in dwelling units must have a window or exterior door for an emergency exit, sill height not more than 44 inches above the floor, 5.7 square feet of openable area, 24 inches clear opening height, 20 inches clear opening width and shall open directly into a public street, alley, yard, or exit court. Windows ______ do not comply. (CRC R310.1-R310.1.3)
CAUTION: Using minimum clear openable height with the clear openable width will yield only 3.3 square feet and not the minimum 5.7 square feet required. Be especially careful with double-hung windows. Also, when the emergency escape window is below ground level refer to CRC Section R310.2 for additional requirements. Show location of heating equipment on the plans. (CRC R303.8)All new construction, interior or exterior alterations, repairs, or additions requiring a permit and having a valuation in excess of $1,000, or when one or more sleeping rooms are added or created, the entire dwelling shall be provided with smoke detectors located as required for a new dwelling. (CRC R314.3) Smoke alarms shall be installed in the following locations:
- In each sleeping room.
- Outside each separate sleeping area in the immediate vicinity of the bedrooms.
- On each additional story of the dwelling, including basements and habitable attics but not
including crawl spaces and uninhabitable attics. In dwellings or dwelling units with split
levels and without an intervening door between the adjacent levels, a smoke alarm
installed on the upper level shall suffice for the adjacent lower level provided that the lower
level is less than one full story below the upper level.
- When more than one smoke alarm is required to be installed within an individual dwelling
unit the alarm devices shall be interconnected in such a manner that the actuation of one
alarm will activate all of the alarms in the individual unit.All new construction, Interior or exterior alterations, repairs, or additions requiring a permit and having a valuation in excess of $1,000,, an approved carbon monoxide alarm shall be installed in dwelling units and in sleeping units within which fuel-burning appliances are installed and in dwelling units that have attached garages shall be provided with carbon monoxide alarms (CRC R315)
- Carbon monoxide alarms shall only be required in the specific dwelling unit or sleeping unit for
which the permit was obtained. Carbon monoxide alarms required by Sections R315.1 and
R315.2 shall be installed in the following locations: ________.
- Outside of each separate dwelling unit sleeping area in the immediate vicinity of the bedroom(s).
- On every level of a dwelling unit including basements.
- Where more than one carbon monoxide alarm is required to be installed within the dwelling unit or
within a sleeping unit the alarm shall be interconnected in a manner that activation of one alarm
shall activate all of the alarms in the individual unit.
Exception:
Interconnection is not required in existing dwelling units where repairs do not result in the removal of wall and ceiling finishes, there is no access by means of attic, basement or crawl space, and no previous method for interconnection existed.For each enclosed attic space with a maximum vertical height greater than 30 inches, provide a minimum of 22 x 30 inches attic access. (CRC R807.1) Callout attic vents locations, sizes and types on plans. Provide attic ventilation calculation to show minimum ventilation is provided. (CRC R806.2)The total net free ventilating area shall not be less than 1/150or 1/300 when a Class I or II vapor barrier is installed on the warm-in-winter side of the ceiling. (CRC R806.2) Provide landing at the sliding door.For roof covering specify type of the materials, and minimum class “C” rating.Show exterior wall construction assembly. A minimum of one layer of No. 15 asphalt felt, free from holes and breaks, complying with ASTM D 226 for Type 1 felt shall be applied over studs of all exterior walls. Specify that two layers of Grade D or 60 minute Grade D paper shall be applied over all wood base sheathing. (CRC R703.2) Specify a minimum 0.019” (No. 26 galvanized sheet gage) corrosion-resistant or plastic weep screed located below foundation plate line and 4 inches above grade on all exterior stud walls or 2-inches above paved areas. (CRC R703.6.2.1)
3”x3”x.229” steel plate washers are required on all anchor bolts in a braced wall line. (CRC R403.1.6.1)
Provide a weep screed for stucco at the foundation plate line a minimum of 4 inches above the earth or 2 inches above paved areas. (2512.1.2)
Detail the shear transfer connections which transfer lateral forces from horizontal diaphragms through intermediate elements and shear walls to the foundation. (1603)
The _____ x _____ rafters at _____o.c. over ______ exceed the allowable span for grade.
Show blocking at ends of rafters and trusses at exterior walls, at supports of floor joists and at the ridge line of truss roofs. CRC R802.8
For plywood roof and floor diaphragm specify thickness, grade, T&G edges, panel span rating, nailing schedule and required blocking and panel layout pattern.
Detail how the interior shearwalls are connected to the roof diaphragm.
The residence shall conform to the State Energy Conservation Standards. Submit forms and calculations for review and blueprint the final forms on the plans.
- Signed Energy Efficiency Documents must be printed on the plans.
- Also, submit 2 copies of signed Energy Efficiency calculations.
- The corrected/final drawings shall have the required energy efficiency compliance documentation
with completed signature blocks filed on the plans.
Show Radiant Barrier, Cool Roofing, Duct Ceiling as required by the 2008 California Energy Residential Manual for prescriptive Package D. For new construction use prescriptive package D or provide a complete performance analysis. (2008 CESC 152(a)) All new windows and doors shall have a label indicating the U-factor and SHGU. Comply with energy documentation requirements.Revise framing plans to indicate insulation for walls R=13, ceiling R=30, and raise floor R=19 climate zone 8. (2008 CESC 150) Provide shear wall on four sides of the addition, with the shear wall schedule.Provide detail for post installed anchor bolts.Provide footing under bearing wall.Call out bracing spacing on section A of sheet A3.