HomeMy WebLinkAbout191666_3_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10180517-518 PROJECT ADDRESS: 1015 E Chestnut Ave Unit# A PLAN CHECK ENGINEER: Ahangian, KathyTEL:714 647-5812FAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): B PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 1/21/2014 INITIAL REVIEW 1/25/2014 EXPIRATION 7/20/2014 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Rob Burns 3. TEL: (949)887-3737 FAX: VALUATION:$27,930.00 EMAIL: RDBINC@YAHOO.COM FLOOD ZONE:X-0602320276J APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2013 California Building Standards Code with local amendments.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Fire Department approval on the corrected/final sets of drawings ((714)573-6100) - Police Department approval on the corrected/final set of drawings (647-5840) - Public Works Agency approval (647-5039) - Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Please fillout attached disabled access compliance form.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.CBC Section 1009.10, Handrails. Stairways shall have handrails on each side and shall comply with Section 1012. Where glass is used to provide the handrail, the handrail shall also comply with Section 2407 of the California Building Code.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B: - An accessible entrance - An accessible route to the altered area - Accessible restrooms - Accessible telephone (if any) - Accessible drinking fountains, and - Parking, signage and alarmsProvide completely dimensioned floor plans, elevations and sections of sanitary facility insuring wheelchair clearances complying with CBC Section 1115B and the California Plumbing Code.CBC Sections 1115B and 1210. Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.CBC Section 1607.7. Provide complete grab bar details on the drawings showing compliance with CBC Section 1115B.8 including structural strength to support a 250 pound point load.CBC Section 1115B.4.3 Item 4. Note on the drawings hot water and drain pipes under lavatory shall be insulated.Show the bathroom is not encroaching more than 12” into 60” clear radius.Provide complete demo plan on the existing floor plan.Provide complete calculation and detail for all the new openings in the front and the back.Please justify the seismic load, with all the new openings.Live load for office is 50psf per Tbl1607.1 , please provide calculation based on the office live load and also , partition walls.Provide roof framing to show the load imposed on the first floor.Provide detail for new walls on the second floor.Provide spacing for stud on detail D/A6.When occupant load exceeds 29 people or travel distance is more than 75 feet, second exit from the second floor is required.