HomeMy WebLinkAbout187162_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10179145
PROJECT ADDRESS:
1919 N Spurgeon St
PLAN CHECK ENGINEER:
Vo, TungTEL:714
647-5830FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
7/1/2013
INITIAL REVIEW
7/25/2013
EXPIRATION
12/28/2013
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Moises Cardenas
3.
TEL:
(818)909-0286
FAX:
VALUATION: $139,039.00
EMAIL:
Cardenasmoises@hotmail.com
FLOOD ZONE: X-0602320163J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2010 California Residential Code (CRC); 2010 California Building Code (CBC); CMC = 2010 California Mechanical Code; CPC = 2010 California Plumbing Code; CEC = 2010 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
- Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
-Police Department approval on the corrected/final set of drawings (647-5840).
-Public Works Agency approval (647-5039).
-Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
- School District Compliance Certificate; and a copy of the building permit application, signed by
the plan check engineer, shall be required by the School District to verify the scope of the work.
-Grading Permit. Application is made through the Building Safety Division (647-5800) and the
plan review is by the Public Works Agency (647-5039).Projections of dwelling units and accessory buildings with an automatic residential fire sprinkler protection are not permitted less than 2 feet to the property line and are required to be 1 hour fire rated on the underside with a fire separation distance between 2 feet and 3 feet. (CRC Table R302.1 (2)) Walls of dwelling units and accessory buildings with an automatic residential fire sprinkler protection with a fire separation distance less than 3 feet are required to have a full one hour rating. (CRC Table R302.1 (2)) Openings are not permitted less than 3 feet to the property line. In dwelling units and accessory buildings without an automatic residential fire sprinkler protection openings are limited to 25 percent the wall area when fire separation distance is greater than 3’ and less than 5’. (CRC R302.1 (1)) Shower compartments and walls above bathtubs with shower heads installed shall be finished with a smooth, nonabsorbent surface to a height of not less than 72” above the floor. (CRC R307.2)Specify ICC approval number and weight per square foot for roof coverings. (CRC R905.3.4 and R905.3.5) Show exterior wall construction assembly. A minimum of one layer of No. 15 asphalt felt, free from holes and breaks, complying with ASTM D 226 for Type 1 felt shall be applied over studs of all exterior walls. Specify that two layers of Grade D or 60 minute Grade D paper shall be applied over all wood base sheathing. (CRC R703.2) Submit two (2) copies of a geotechnical report for the subject project in accordance with CBC Section 1802. The geotechnical engineer shall include in said report applicable items noted under CBC Section 1803.6.
CBC Section 1803. Geotechnical report recommendations are considered to be minimum standards. Structural calculations and drawings must meet or exceed said minimum standards. Show compliance with the following geotechnical report recommendations:The construction documents shall provide sufficient clarify to indicate the location, nature, and scope of the proposed green building features. CGBC 102.2Plans shall indicate method of verification of compliance with all CALGreen requirements. Third party or other methods shall demonstrate satisfactory conformance with mandatory measures. Include City's Mandatory Measures Checklist copies onto plans.Show exhaust hood and exhaust vent above cooking appliances at the kitchen. (CMC 504.2) At least one outlet to be installed at the front and rear of each dwelling unit. (CEC 210.52(E))
Correction is ready to pick up at the counter. Please see additional corrections on plan and calculation. Additional corrections may follow when revised plan resubmitted.