HomeMy WebLinkAbout193961_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10181215
PROJECT ADDRESS:
1346 S Magnolia Ave
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/30/2014
INITIAL REVIEW
5/11/2014
EXPIRATION
10/27/2014
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Araceli Maciel
3.
TEL:
(714)835-1428
FAX:
VALUATION: $53,955.00
EMAIL:
aadrafting@msn.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2010 California Residential Code (CRC); 2010 California Building Code (CBC); CMC = 2010 California Mechanical Code; CPC = 2010 California Plumbing Code; CEC = 2010 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper.
Provide eave / overhang / projection setback to all property lines.Shower compartments and walls above bathtubs with shower heads installed shall be finished with a smooth, nonabsorbent surface to a height of not less than 72” above the floor. (CRC R307.2)Specify a minimum 0.019” (No. 26 galvanized sheet gage) corrosion-resistant or plastic weep screed located below foundation plate line and 4 inches above grade on all exterior stud walls or 2-inches above paved areas. (CRC R703.6.2.1)
Sill plates supporting shear walls with lateral loads greater than 350 pounds/foot require a 3-inch nominal or greater member. (T2306.3, Footnote i)
Detail how the interior shear walls are connected to the roof/floor diaphragm(s). (1603)Note on plans that “Field-cutting ends, notches and drilled holes of preservative-treated wood shall be treated in the field in accordance with AWPA M4”. (CRC R317-1.1) Show window in new bathroom is tempered.Show under floor access for existing sfd.Provide hold down at each end of 4 wall, please see red mark.Show ceiling joist on entire roof framing.Provide strap to existing sfd with detail.Show existing hip can carry additional load from the California roof.Provide dimension to show exact location of king post on the lower beamDetail 17/SD1 doesn’t match the location on the framing plan.