HomeMy WebLinkAbout192979_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10180931
PROJECT ADDRESS:
1600 N Broadway Unit# 200
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
I A, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
3/19/2014
INITIAL REVIEW
3/29/2014
EXPIRATION
9/15/2014
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
M. Steven Camp
3.
TEL:
(949)488-0865
FAX:
(949)488-0864
VALUATION:$129,000.00
EMAIL:
stevenc@elementsarch.com
FLOOD ZONE:X-0602320163J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuancePlease fillout attached disabled access compliance form.Provide typical section view detail of all new partitions and ceilings showing:
- Size, spacing, and material of framing members
- Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13
for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations
and drawing prepared by a registered engineer are submitted for review. Submit structural engineering
calculations for walls in rooms with a floor to building structure above height greater than 14’.
- Heights of partition, suspended ceiling, structure above.Provide ICC report and span table for metal studs,EXIT ACCESS. That portion of a means of egress system that leads from any occupied portion of a building or structure to an exit. CBC Sections 1002 and 1014.Egress from a room or space shall not pass through adjoining or intervening rooms or areas, except where such adjoining rooms or areas are accessory to the area served, are not high hazard occupancy and provide a discernible path of egress travel to an exit.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Provide minimum clearance 12” at the breakroom door, office #210 and also provide 18” clearance to the strike edge of door 211A. (please see red marks)Exit illumination and exit sign requirements in accordance with CBC Section 1011 shall be shown on the drawings. Be specific as to the type of exit signs to be installed.CBC Section 1011.1. Provide a directional exit sign at changes in exiting direction.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of a stairway or ramp shall be
identified by a tactile exit sign with the following words as appropriate:“EXIT STAIR DOWN”“EXIT RAMP DOWN”“EXIT STAIR UP”“EXIT RAMP UP”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”For the purpose of Section 1011.3, the term “tactile exit signs” shall mean those required signs that comply with Section 1117B.5.1, Item 1.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 1133B.8.5.
Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC Section 1133B.8.5.Complete the attached Disabled Accessibility Documentation Form.Is T-Bar ceiling new or existing , on ceiling plan It shows existing but on detail 1/A8.2 shows new please clarify. If it is new please see comment following comments.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636. (OR SEE COMMENTS 23-25)Provide a complete suspended ceiling system plan and section detail showing the following:
- Vertical supports
- Seismic wires
- Seismic strut/Compression strut
- Perimeter wires
- Separate fixture wires for lights and mechanical devices
- ICC Research Report number for the suspended ceilingThe reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)On detail 2/A8.2 , please show:-Size of the Hilti bolts-attachment detail to the structure above.