HomeMy WebLinkAbout193456_3_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10181062 PROJECT ADDRESS: 2200 3/4 E Mcfadden Ave Unit# WCC01 PLAN CHECK ENGINEER: Mazarji, ZacTEL:714 647-5831FAX:714 647-5897 TYPE OF CONSTRUCTION: N/A OCCUPANCY CLASSIFICATION(S): N/A PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 4/8/2014 INITIAL REVIEW 4/14/2014 EXPIRATION 10/5/2014 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Allen Rolison 3. TEL: (949)398-8050 FAX: VALUATION:$75,000.00 EMAIL: arolison@sbasite.com FLOOD ZONE:X-0602320277J APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Please return marked up set of drawings with corrections.(When needed) Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5831 for an appointment.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Public Works Agency approval (647-5039) - Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceReference structural calculations dated Nov. 19, 2013; revise calculations to show compliance with 2013 CBC, including notes on sheet 3 of calculations. Also revise drawings as well.All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer. Structural calculations and drawings to be signed and stamped by the same engineer. Each engineer submitting structural calculations to incorporate the results of calculations into signed and stamped drawings. CBC Sections A106.1 and A106.3.4.1. (Drawings are signed and stamped by a different engineer who is signed structural calculations). Provide calculations for design and justification of existing pole, attachment and foundation system. Provide as built/existing drawings. Section 3404.4 of CBC, where the alteration increases design lateral load.   Any existing lateral load carry structural elements whose demand-capacity ratio with the alteration considered is no more than 10 percent grater its demand-capacity ratio with the alteration ignored shall be permitted to remain unaltered. Submit structural calculations for design and justification to determine compliance with said Section. CBC Section 1603.1.4, Wind design data. The following information related to wind loads shall be shown, regardless of whether wind loads govern the design of the lateral-force-resisting system of the building: - Basic wind speed (3-second gust), miles per hour (km/hr). - Wind importance factor, I, and occupancy category. - Wind exposure. Where more than one wind exposure is utilized, the wind exposure and applicable wind direction shall be indicated. - The applicable internal pressure coefficient. - Components and cladding. The design wind pressures in terms of psf to be used for the design of exterior component and cladding materials not specifically designed by the registered design professional.CBC Section 1603.1.5, Earthquake design data. The following information related to seismic loads shall be shown, regardless of whether seismic loads govern the design of the lateral-force-resisting system of the building: - Seismic importance factor, I, and occupancy category. - Mapped spectral response accelerations, SS and S1. - Site class. - Spectral response coefficients, SDS and SD1. - Seismic design category. - Basic seismic-force-resisting system(s). - Design base shear. - Seismic response coefficient(s), CS. - Response modification factor(s), R. - Analysis procedure used.