HomeMy WebLinkAbout195187_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10181634
PROJECT ADDRESS:
611 W Civic Center Dr Unit# 301
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/12/2014
INITIAL REVIEW
7/16/2014
EXPIRATION
12/9/2014
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Roberto Lapeyre
3.
TEL:
(562)810-0626
FAX:
VALUATION:$10,000.00
EMAIL:
roi@imaginario.us
FLOOD ZONE:X-0602320163J
APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. This requirement applies to both exempt and non-exempt projects. Business and Professions Code Chapter 3, Division 3, Section 5536.1(a).Include address and telephone number of the responsible designer, and date of signing of drawings.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Police Department approval on the corrected/final set of drawings (647-5840)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceShow complete floor plan for the adjacent unit.Provide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.
- Show all property lines of record on the site plan. Show compliance with CBC Section 704 and CBC Tables
601, 602, and 704.8.Provide complying exiting plan for the “remainder” area. Note the use of adjacent units.CBC Section 1016.1. Travel distance limitations. Exits shall be so located on each story such that the maximum length of exit access travel, measured from the most remote point within a story to the entrance to an exit along the natural and unobstructed path of egress travel, shall not exceed the distances given in Table 1016.1.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsCBC Section 1114B.1.2, 1114B.1.3. and 1129B.3, Item 3. Entrance(s) to the building or facility and primary path of travel to the specific area of new work, alteration, structural repair or addition shall be accessible. Path of travel incorporated all elements from the exterior arrival site to remodeled area.Each lot or parking structure where parking is provided for the public as clients, guest or employees, shall provide accessible parking as required by CBC Section 1129B.Please fill out attached disabled compliance form.