HomeMy WebLinkAbout194277_2_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10181331 PROJECT ADDRESS: 1730 E Seventeenth St Unit# D PLAN CHECK ENGINEER: Mazarji, ZacTEL:714 647-5831FAX:714 647-5897 TYPE OF CONSTRUCTION: V A OCCUPANCY CLASSIFICATION(S): B PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 5/12/2014 INITIAL REVIEW 5/22/2014 EXPIRATION 11/8/2014 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Seung Hwan Pak 3. TEL: (213)500-3638 FAX: VALUATION:$59,165.00 EMAIL: spinteriordesign76@gmail.com FLOOD ZONE:X-0602320164J APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Resubmit 3 corrected sets of plans.(When meeting is needed) Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5831 for an appointment.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 714-647-5800 for information. Please remove electrical, mechanical and plumbing sheets.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Public Works Agency approval (647-5039) - Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceAll persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. Please note type of construction on drawing as V-A (1 hour) based on City records.Reference each fire-resistive assembly to a CBC Chapter 7, Table and Item number: - Walls - Ceilings - ColumnsPlans shall indicate how required structural and fire resistive integrity will be maintained where a penetration will be made for electrical, mechanical, plumbing and communication conduits, pipes and similar systems. CBC Section 106.1.1 and CBC Chapter 7. Note on the plans the ICC Research Report number, U.L. number, State Fire Marshal number, or approval number of another agency accepted by the City of Santa Ana. Provide a complete site plan on each set of drawings. Also Provide parking data on the site plan showing the total number of parking spaces provided the number of disabled accessible spaces and the number of van accessible spaces. Provide truncate domes to cove the accessible parking stall landing. If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 1133B.8.5. Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC Section 1133B.8.5. Provide natural ventilation per section 1203.4 and natural or artificial lighting per section 1205 of CBC. In lieu of natural ventilation provide mechanical ventilation per California Mechanical Code. Note on the floor plan the use and occupancy load of each room and/or area. Relate each use to a CBC Table 1004.1.1. Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B: Provide additional drawings to insure compliance with followings: - An accessible entrance - An accessible route to the altered area - Accessible restrooms - Accessible telephone (if any) - Accessible drinking fountains, and - Parking, signage and alarmsValuation of proposed project is calculated as $59,165.00. A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in the immediate previous item as noted in CBC Section 1134B. Revise the drawings to show compliance. Show both existing elements and how they will be upgraded to current standards.Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.CBC Section 1115B.4.3 Item 4. Note on the drawings hot water and drain pipes under lavatory shall be insulated.Separate, disabled accessible, sanitary facilities shall be provided for each gender in accordance with the California Plumbing Code (CPC) . Show compliance with Table 422.1 of CPC for required number of toilet rooms. Indicate occupancy for existing building and indicate occupant load to establish required number of toilet rooms for this project.Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.CBC Section 1607.7. Provide complete grab bar details on the drawings showing compliance with CBC Section 1115B.8 including structural strength to support a 250 pound point load.Note on the drawings hot water and drain pipes under lavatory shall be insulated.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards. City of Santa Ana does not have jurisdiction to enforce ADA compliance and it is the responsibility of designer. If applicable please remove notes referring to ADA compliance from drawings. This project is reviewed for compliance with State Accessibility Standards (T-24).