Loading...
HomeMy WebLinkAbout199018_1_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10182836 PROJECT ADDRESS: 4041 W Garry Ave PLAN CHECK ENGINEER: Mazarji, ZacTEL:714 647-5831FAX:714 647-5897 TYPE OF CONSTRUCTION: N/A OCCUPANCY CLASSIFICATION(S): N/A PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 10/13/2014 INITIAL REVIEW 10/16/2014 EXPIRATION 4/11/2015 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Scott Harris 3. TEL: (909)359-8165 FAX: VALUATION:$250,000.00 EMAIL: scottharris@visionce.com FLOOD ZONE:X-0602320258JAll items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction.Resubmit 3corrected sets of signed and stamped plans. When meeting is needed, meetings between the project applicant/designer and the plan reviewer shall be by appointment only. This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information. Please remove electrical, Mechanical and Plumbing drawings.The applicant shall obtain clearances/approvals for the following, prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process. - Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2013 California Building Standards Code with local amendments.Provide roof framing plan (as built on the drawings) on each set of plan.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.Submit structural calculations by a licensed architect or engineer for complete vertical and lateral load analysis for new solar panels on the roof.Indicate ICC approved sealing for all roof penetrations.