HomeMy WebLinkAbout199657_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10183075
PROJECT ADDRESS:
527 E Virginia Ave
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/12/2014
INITIAL REVIEW
12/15/2014
EXPIRATION
5/11/2015
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Aaron O'Neil
3.
TEL:
(714)871-1047
FAX:
VALUATION: $8,300.00
EMAIL:
aaron@appliedses.com
FLOOD ZONE: X-0602320163J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2013 California Residential Code (CRC); 2013 California Building Code (CBC); CMC = 2013 California Mechanical Code; CPC = 2013 California Plumbing Code; CEC = 2013 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2010 California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Please note weight of the Ballast tray and solar panel on the drawings.
Provide roof framing plan.
Nonstructural components and their supports shall be attached (or anchored)to the structure in accordance with the requirements of ASCE 7-10 ,13.4.
A continuous load path of sufficient strength and stiffness between the component and the supporting structure shall be provided,
Please justify existing members can support additional load from the ballast.