HomeMy WebLinkAbout198522_2_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10182663 PROJECT ADDRESS: 1421 W MacArthur Blvd Unit# F PLAN CHECK ENGINEER: Ahangian, KathyTEL:714 647-5812FAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): B PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 9/24/2014 INITIAL REVIEW 11/2/2014 EXPIRATION 3/23/2015 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Phil Nguyen 3. TEL: (949)910-7768 FAX: VALUATION:$43,000.00 EMAIL: philnguyen_69@yahoo.com FLOOD ZONE:X-0602320258J APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2013 California Building Standards Code with local amendments.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Public Works Agency approval (647-5039) - County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000)- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide the following: - Provide a fully dimensioned site plan on each set of plans. - Disabled access compliance must be shown on the site plan. - Provide a fully dimensioned site plan on a separate 8½” x 11” sheet of paper. - Show all property lines of record on the site plan. Show compliance with CBC Section 704 and CBC Tables 601, 602, and 704.8.Show entrance on the site plan.Show path of travel from disabled parking to the entrance.Enlarge path of travel to show compliance with disabled access.Submit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Provide typical section view detail of all new partitions and ceilings showing: - Size, spacing, and material of framing members - Note gauge and ICC Research Report number and installation/construction requirements for metal framing members. - Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13 for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations and drawing prepared by a registered engineer are submitted for review. Submit structural engineering calculations for walls in rooms with a floor to building structure above height greater than 14’. - Heights of partition, suspended ceiling, structure above.Provide wall legend to show new, existing and demo wall.Complete all soffit and furred out wall details. Provide complete detailing, including number, type, location of fasteners and how attachment is made to the building structure. Show compliance with CBC Section 803.Provide on the drawings a complete door schedule, showing: - Door sizes (CBC Sections 1008.1.1 and 1133B.2) - Hardware complying with exiting and disabled accessibility requirements (CBC Sections 1008.1.8 and 1133B.2.5)Provide elevation to show cashier is in compliance with disabled access.Please fill out attached disabled access compliance form.Provide minimum 18” clearance to strike edge of the kitchen door.Bathroom door cannot encroach more than 12” into clear radius.Show minimum 24” from the toilet to the end of grab bar.Show minimum 7”-9” clearance from toilet to the bathroom tissue.Provide detail for the grab bar to show support of 250lb load.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Provide minimum 48” landing on right side door.Exit illumination and exit sign requirements in accordance with CBC Section 1011 shall be shown on the drawings. Be specific as to the type of exit signs to be installed.Tactile exit signs shall be required at the following locations: - Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.” - Each exit door that leads directly to a grade-level exterior exit by means of a stairway or ramp shall be identified by a tactile exit sign with the following words as appropriate: If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 1133B.8.5. Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC Section 1133B.8.5.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636. (OR see comment # 31-32 )The reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)Provide complete construction detail for drywall ceiling.Provide complete detail for soffit to show vertical and lateral support.Show 2 end support for the beam shown on section C/A3.Call out detail 5/A4 on plan view.