PLAN CHECK NO:
10184718
PROJECT ADDRESS:
724 S Harbor Blvd
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
A-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/9/2015
INITIAL REVIEW
4/22/2015
EXPIRATION
10/6/2015
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Hoang Pham
3.
TEL:
(714)495-0056
FAX:
VALUATION:$96,427.00
EMAIL:
hdpconstruction@yahoo.com
FLOOD ZONE:X-0602320256J
APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.Include address and telephone number of the responsible designer, and date of signing of drawings.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Public Works Agency approval (647-5039)
- County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Provide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.Show on the plans:
- Complete legal description
- Fire Sprinkler System (State purpose of sprinkler system, for example, area increase under CBC Section
506.3, required by CBC Section 903 for type of occupancy, etc.)Panic hardware shall comply with CBC Section 1008.1.9. Panic hardware shall be provided as required by CBC Section(s):
- An Occupancy with an occupant count > 50. Refer to CBC section 1008.1.8.3, Item 2 for Exception.
- By the Fire Department CBC Section 1133B.2.5.1, Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Show minimum 12 inch clearance to the strike edge of door #D4 in office.CBC Section 1011.1. Provide a directional exit sign at changes in exiting direction.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of a stairway or ramp shall be
identified by a tactile exit sign with the following words as appropriate:“EXIT STAIR DOWN”“EXIT RAMP DOWN”“EXIT STAIR UP”“EXIT RAMP UP”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible drinking fountains, and
- Parking, signage and alarmsIf a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 1133B.8.5.
Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC Section 1133B.8.5.CBC Section 1607.7. Provide complete grab bar details on the drawings showing compliance with CBC Section 1115B.8 including structural strength to support a 250 pound point load.CBC Section 1115B.4.3 Item 4. Note on the drawings hot water and drain pipes under lavatory shall be insulated.Show disabled toilet stalls are in compliance with figure 11B-604.8.1.1.2Show urinal is in compliance with disabled access, provide clear floor space for the urinal.All dining, banquet, and bar facilities shall be made accessible to persons with disabilities as provided in CBC Section 1104B.5. At least 5%, but not less than one of the seating spaces in each functional area is accessible as follows:
- Provide a minimum 30” x 48” wheelchair clear floor space.
- Provide knee space at tables at least 27” high, 30” wide and 19” deep.
- Provide height of tables between 28” – 34” from the floor ground.
- Provide access to accessible seating space(s) by aisles with a minimum of 36” in width.CBC Section 1122B.1. Where a single counter contains more than one transaction station, such as (but not limited to) a bank counter with multiple teller windows or a retail sales counter with multiple cash register stations, at least 5 percent, but never less than one, of each type of station shall be located at a section of counter that is at least 36” long and no more than 28 to 34” high.Complete the attached Disabled Accessibility Documentation Form.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636. (Or See comment # 26-27)The reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)Show height of the storage racks, for storage racks between 6 to 8 feet high, provide attachment detail.Provide complete ceiling detail for ceiling E an D on sheet A4.Provide ICC report and span table for Ceiling joists.Show existing floor plan.Show how the soffit is being supported laterally.