HomeMy WebLinkAbout205283_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10184932
PROJECT ADDRESS:
3202 S Shannon St
PLAN CHECK ENGINEER:
Heidari, FredTEL:714
647-5862FAX:714
647-5897
TYPE OF CONSTRUCTION:
III B, SPK
OCCUPANCY CLASSIFICATION(S):
B, S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/29/2015
INITIAL REVIEW
5/13/2015
EXPIRATION
10/26/2015
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Don Beechan
3.
TEL:
(949)852-5900
FAX:
(949)852-5909
VALUATION:$114,521.00
EMAIL:
don@mvaarc.com
FLOOD ZONE:X-0602320258J
APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceThe width of the level area on the side to which the door swings shall extend 24” past the strike edge of the door for exterior doors.Show compliance for the main entry door shown on sheet SP.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Sanitary facilities serving the area of new work shall be disabled accessible. On the enlarged toilet room plan, please show all clearances and maneuvering spaces called out in CBC Sections: 11B-603 and 11B-604.Provide aroof plan and show the roof mounted equipment with proper construction details for their attachments.Show compliance with CBC Section 2406.4.2, glazing adjacent to door, for the following rooms on the plan; room # 103, 107, & 113.