HomeMy WebLinkAbout204781_2_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10184754 PROJECT ADDRESS: 1400 N Main St PLAN CHECK ENGINEER: Heidari, FredTEL:714 647-5862FAX:714 647-5897 TYPE OF CONSTRUCTION: V B, SPK OCCUPANCY CLASSIFICATION(S): B PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 4/14/2015 Items # 7, 14, 24, 25, & 27 are not done at this time. INITIAL REVIEW 4/21/2015 EXPIRATION 10/11/2015 RECHECKS: 1. 05/18/2015 PROJECT APPLICANT CONTACT PERSON: 2. Maria Gomez 3. TEL: (323)726-7734 FAX: VALUATION:$110,823.00 EMAIL: maria@barrioplanners.com FLOOD ZONE:X-0602320163J APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2013 California Building Standards Code with local amendments.Sheets G002, 003, & 004 shall be cleaned up and updated to show only the accessibility notes that are under chapter 11B as they apply to commercial buildings and only the ones that are in CBC 2013. See red marks on these sheets. The accessible stalls shown on sheet AS101 do not comply with Section 11B-208 of CBC 2013.Please justify why this facility should not comply with Sections 11B-208.2.1 & 11B-208.2.2 of CBC 2013.Show compliance with Section 11B-208.2.4 for number of van parking spaces.Show compliance with Table 422.1 CPC 2013 for minimum plumbing facilities.Delete all notes and details from drawings that are not a part of the work to be done under the subject building permit application. All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Police Department approval on the corrected/final set of drawings (647-5840) - Public Works Agency approval (647-5039) - Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide typical section view detail of all new partitions and ceilings showing: - Size, spacing, and material of framing members - Note gauge and ICC Research Report number and installation/construction requirements for metal framing members. - It is the project designer’s responsibility to coordinate work with the various trades to ensure that the size of the wall cavity will be large enough to accommodate piping, fittings, ducts, etc. There has been a continuing field problem of 2½” wide metal studs not being able to accommodate plumbing pipes. - Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13 for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations and drawing prepared by a registered engineer are submitted for review. The legend on sheet A102 calls for interior walls to be framed with steel studs, and detail 4/A301is calling and showing a wood framed wall. Please provide coordination between the detail and the legend.Note on drawing: “Exit doors shall be openable from the inside without the use of a key or any special knowledge or effort.”All doors require a level floor landing on each side in accordance with CBC. Provide typical door threshold details and details of change in floor covering material.The width of the level area on the side to which the door swings shall extend 24” past the strike edge of the door for exterior doors and 18” past the edge for interior doors. CBC Chapter 11B.Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Requires exit signs to be readily visible from any direction of approach. No point shall be more than 100’ from the nearest visible exit sign. Revise the drawings to show compliance for the combined suites, “A”& “B”.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Chapter 11B: - An accessible entrance - An accessible route to the altered area - Accessible restrooms - Accessible telephone (if any) - Accessible drinking fountains, and - Parking, signage and alarmsValuation of proposed project is calculated as $ 110,823.00. A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in the immediate previous item as noted in CBC Chapter 11B. Revise the drawings to show compliance. Show both existing elements and how they will be upgraded to current standards.Walks and sidewalks shall not have cross slopes exceeding ¼” per foot (2% slope). Slopes along the path of travel shall not exceed 5% unless designed as a pedestrian ramp in accordance with CBC.If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC. Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC Section 11B-705.3.Separate, disabled accessible, sanitary facilities shall be provided for each gender in accordance with the California Plumbing Code (CPC) and CBC.See red marks on the following sheets: G005, AS101, A102, A202, & A301. Please resubmit the marked up plan with revised ones for recheck.