HomeMy WebLinkAbout205762_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10185109
PROJECT ADDRESS:
711 N Bristol St
PLAN CHECK ENGINEER:
Heidari, FredTEL:714
647-5862FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
A-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
5/18/2015
INITIAL REVIEW
06/18/2015
EXPIRATION
11/14/2015
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Earl Ammerman
3.
TEL:
(951)352-3588
FAX:
VALUATION:$15,000.00
EMAIL:
info@powellandassoc.com
FLOOD ZONE:X-0602320144J
APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.This review does not include mechanical, plumbing, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Orange County Fire Authority approval on the corrected/final sets of drawings ((714)573-6100)
- Public Works Agency approval (647-5039)
- County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide information for relocated hood and how it will be secured to the existing roof. Provide on the drawings a complete door schedule, showing:
- Door sizes
- Hardware complying with exiting and disabled accessibility requirementsNote on drawing: “Exit doors shall be openable from the inside without the use of a key or any special knowledge or effort.”Exit doors shall swing in the direction of exit travel when serving any hazardous area or when serving an occupant load of 50 or more.Provide specifications for doors hardware (i.e., lever type, push-pull panic, etc) to comply with disabled access requirements. CBC chapter 11B.Regardless of the occupant load, there shall be a floor or landing on each side of a door. The floor or landing shall be not more than ½” lower than the threshold of the doorway. Change in level between ¼” and ½” shall be beveled with a slope no greater than 1:2. Change in level greater than ½” shall be accomplished by means of a ramp. Provide detailed sections and plan views showing compliance at all doorways requiring accessibility.Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. The bottom 10” of all doors except automatic and sliding shall have a smooth uninterrupted surface to allow the door to be opened by a wheelchair footrest without creating a trap or hazardous condition.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsValuation of proposed project is calculated as $15000.00. A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in the immediate previous item as noted in CBC chapter 11B. Revise the drawings to show compliance. Show both existing elements and how they will be upgraded to current standards.Entrance(s) to the building or facility and primary path of travel to the specific area of new work, alteration, structural repair or addition shall be accessible. Path of travel incorporated all elements from the exterior arrival site to remodeled area.Accessible parking spaces serving a particular building shall be located on the shortest accessible route of travel from adjacent parking to an accessible entrance.