PLAN CHECK NO:
10285138
PROJECT ADDRESS:
1617 N Linwood Ave
PLAN CHECK ENGINEER:
So, AnsonTEL:714
647-5830FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
5/19/2015
INITIAL REVIEW
7/10/2015
EXPIRATION
11/15/2015
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Jose De Jesus Pena
3.
TEL:
(714)835-9114
FAX:
VALUATION: $42,696.00
EMAIL:
Jose0258@att.net
FLOOD ZONE: X-0602320163J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2013 California Residential Code (CRC); 2013 California Building Code (CBC); CMC = 2013 California Mechanical Code; CPC = 2013 California Plumbing Code; CEC = 2013 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.Sheet 1Revise the governing Code to 2013 California Residential Code (CRC) under note #1.Revise the fastener schedule reference to 2013 CRC Table R602.3(1) under note #2.Specify “Sprinkler: Yes or No?” under Building Data.Separate occupancy groups “R3” and “U” under Building Data.Provide energy documentation on plan.Provide “Drawing Index” on the title sheet.Sheet 2Provide exhaust fan with minimum 50 cfm in the bathroom.Cross reference detail number at exterior landing.Specify landing dimension on the plan.
R311.3 Floors and landings at exterior doors. There shall be a landing or floor on each side of each exterior door. The width of each landing shall not be less than the door served. Every landing shall have a minimum dimension of 36 inches measured in the direction of travel. Exterior landings shall be permitted to have a slope not to exceed ¼ unit vertical in 12 units horizontal (2 percent)
Exception: Exterior balconies less than 60 square feet and only accessible from a door are permitted to have a landing less than 36 inches measured in the direction of travel.Specify minimum clearance dimension at water closet.
2010 CPC Section 407.5 Setting.Fixtures shall be set level and in proper alignment with reference to adjacent walls. No water closet or bidet shall be set closer than fifteen (15) inches from its center to any side wall or obstruction nor closer than thirty (30) inches center to center to any similar fixture. The clear space in front of any water closet or bidet shall be not less than twelve-four (24) inches. No urinal shall be set closer than twelve (12) inches from its center to any wall or partition nor closer than twenty-four (24) inches center to center.
Exception: The installation of paper dispensers or accessibility grab bars shall not be considered obstructions.Sheet 3Provide attic ventilations and foundation calculations analysis and design.
R806.2 Minimum vent area. The minimum net free ventilation area shall be 1/150 of the area of the vented space.
Exception: The minimum net free ventilating area shall be 1/300 of the area of the vented space provided one or more of the following conditions are met:
In Climate Zones 14 and 16, a Class I or II vapor retarder is installed on the warm-in-winter side of the ceiling.
At least 40 percent and not more than 50 percent of the required ventilating area is provided by ventilators located in the upper portion of the attic or rafter space. Upper ventilators shall be located no more than 3 feet below the ridge or highest point of the space, measured vertically, with the balance of the required ventilation provided by eave or roof framing members conflicts with the installation of upper ventilators, installation more than 3 feet below the ridge or highest point of the space shall be permitted.
Sheet 4Show framing size and spacing on the plan. Are there pier and foundation system at the mid-span of floor joist?
Sheet 5Reference opening detail on framing plan.Cross reference all structural details from the framing plan.Provide connection detail between hip-beam and top of wall.Provide connection detail between hip-beam and ridge broad.Provide connection detail at king post top and bottom connection.Reference connection detail between rafters and ridge broad.Provide shear transfer detail at interior wall near the new bathroom.Provide braced wall at new bathroom location.Update fastener schedule to 2013 CRC TableR602.3(1).Specify length of braced walls.
Sheet 6
Detail 6 – Plan shows 2x10 ridge board. However, detail shows 2x12 ridge board. Verify discrepancy.
Detail 6 – Plan shows 2x8 roof rafter. However, detail shows 2x10 roof rafter. Verify discrepancy.