HomeMy WebLinkAbout204443_3_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10184624
PROJECT ADDRESS:
1246 S Olive St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/1/2015
INITIAL REVIEW
4/15/2015
EXPIRATION
9/28/2015
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Jesus Jacobo
3.
TEL:
(714)531-1995
FAX:
VALUATION: $23,326.00
EMAIL:
jfjacobo@gmail.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2013 California Residential Code (CRC); 2013 California Building Code (CBC); CMC = 2013 California Mechanical Code; CPC = 2013 California Plumbing Code; CEC = 2013 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper. Shower compartments and walls above bathtubs with shower heads installed shall be finished with a smooth, nonabsorbent surface to a height of not less than 72” above the floor. (CRC R307.2)Interior spaces intended for human occupancy shall be provided with heating facilities capable of maintaining a room temperature of 68 degrees Fahrenheit at a point 3 feet above the floor and 2 feet from exterior walls in all habitable rooms. (CRC R303.8) (35000 BTU is not sufficient for the new addition)Access shall be provided to all under-floor spaces. The floor access shall be a minimum 18” by 24” and openings through a perimeter wall shall be not less than 16” by 24”. (CRC R408.4) (For new and existing house)Specify a minimum 0.019” (No. 26 galvanized sheet gage) corrosion-resistant or plastic weep screed located below foundation plate line and 4 inches above grade on all exterior stud walls or 2-inches above paved areas. (CRC R703.6.2.1)
3”x3”x.229” steel plate washers are required on all anchor bolts in a braced wall line. (CRC R403.1.6.1)
Per LARR 25818 report , the grade of anchor bolt and anchor bolt embedment and edge distance must be specified by the engineer of the record , since there is no engineer is involved in this project , please revise type of the post installed anchor bolt for the new shear wall with approved ICC report.
Detail how the interior shear walls are connected to the roof/floor diaphragm(s). (1603)
The City has encountered a large number of inspection problems arising from a lack of specific framing details. The following listed items are required to be shown on the plans (CBC 107.1):
- All plumbing walls are to be framed with a minimum of 6" studs.
- Double walls used as plumbing walls are to be a minimum of 8" wide and no "flat" studs permitted.
Staggered studs are acceptable.
- Permissible notching and boring of joists are to be shown on the plans and shall not exceed CBC
Section 2308.10.4.2 allowances.
- Notching of exterior and bearing/nonbearing walls shall not exceed 25%/40% respectively. Bored
holes in bearing/nonbearing walls shall not exceed 40%/60% respectively. In no case shall the
edge of the bored hole be nearer than 5/8 inch to the edge of the stud. (2308.9.10 and 2308.9.11)
- Header and trimmer details for doors and windows are to be shown with full length trimmers,
specifying the size of the header and trimmer. (2308.10.4.3)
- All framed buildings which are required to be designed by an engineer or architect must be signed
prior to submission into plan check
- All stud bearing walls are required to comply with the minimum requirements for load bearing walls.
Show location(s) and provide typical construction details. (2308.9)
- Other methods may be used provided a satisfactory engineering and/or architectural design is
submitted.Note on plans that “Field-cutting ends, notches and drilled holes of preservative-treated wood shall be treated in the field in accordance with AWPA M4”. (CRC R317-1.1) Addition to existing building using the prescriptive approach shall meet the requirements of package A of energy 2013. Please show all the details on the framing section.All new windows and doors shall have a label indicating the U-factor and SHGU. Comply with energy documentation requirements.Please fillout attached SB 407 form and copy it on the drawings.