HomeMy WebLinkAbout208639_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10186115
PROJECT ADDRESS:
2022 E Seventeenth St
PLAN CHECK ENGINEER:
Mazarji, ZacTEL:714
647-5831FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/19/2015
INITIAL REVIEW
8/21/2015
EXPIRATION
2/15/2016
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Judy Yam
3.
TEL:
(626)675-9882
FAX:
VALUATION:$93,950.00
EMAIL:
Meiyeeyam@sbcglobal.net
FLOOD ZONE:X-0602320164J
APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. A separate sheet for response may be used.Resubmit 3corrected sets of plans. Please refer to drawings for additional plan check comments. Return marked up set of drawings with corrections.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProposed work is missing site plan including accessible site and path of travel compliance. Complete dimensioned floor plan of actual layout of toilet rooms is required to insure compliance. Entrance(s) to the building or facility and primary path of travel to the specific area of new work, alteration, structural repair or addition shall be accessible. Path of travel incorporated all elements from the exterior arrival site to remodeled area.At every entrance and at every major junction along or leading to an accessible route of travel, there shall be a sign displaying the international symbol of accessibility. Signs shall indicate the direction to accessible building entrances and facilitiesDrawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC /Chapter 11B, Division 2 of 2013 CBC:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsPlease complete attached accessibility form to insure compliance.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards. City of Santa Ana does not have jurisdiction to enforce ADA compliance and it is the responsibility of designer. If applicable please remove notes referring to ADA compliance from drawings. This project is reviewed for compliance with State Accessibility Standards. 2013 CBC with July amendments.Provide the followings to insure new or existing door compliance:All doors require a level floor landing on each side. Provide typical door threshold details and details of change in floor covering materialAll entrances and exterior ground-floor exit doors to buildings and facilities shall be made accessible to persons with disabilities. Doorways shall have a minimum clear opening of 32” with the door open 90 degrees, measure between the face of the door and the opposite stop. Doorways require dimensioning on the plans to insure compliance with the required landing area/maneuvering clearances at doors. Hand-activated door opening hardware shall be centered between 34” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.All building entrances that are accessible to and usable by persons with disabilities shall be identified with a least one standard sign and with an additional directional signs, as required, to be visible to persons along approaching pedestrian ways.Required the bottom 10” of all doors except automatic and sliding shall have a smooth uninterrupted surface to allow the door to be opened by a wheelchair footrest without creating a trap or hazardous condition.Tactile exit signs shall be required at the following locations: Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”Provide parking data on the site plan showing the total number of parking spaces provided, the number of disabled accessible spaces and the number of van accessible spaces, showing compliance with CBC Division 5 of 2013 CBC.provide truncate domes where marked on the drawings and provide enlarged plan of walkway areas. If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC, Division 7.
Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed. Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.Note on the drawings hot water and drain pipes under lavatory shall be insulated.Bank counters, employee work areas including break room shall be made accessible to persons with disabilities as provided in Division 2 of 2013 CBC. At least 5%, but not less than one of in each functional area is accessible as follows: (Please refer to red marks on the drawings)
- Provide a minimum 60” circle wheelchair clear floor space.
- Provide knee space at tables at least 27” high, 30” wide and 19” deep.
- Provide height of tables between 28” – 34” from the floor ground.
- Provide minimum of 32” clearance for entry. Other counters are required to complyShow/note ventilation requirements on the plans in accordance with the CBC and California Mechanical Code (CMC) requirements for each type of use.
Note on drawings: - Provide mechanical ventilation for each area/room in accordance with the 2013 California MechanicalCode. Note on drawings: Show/note LIGHTING requirements on the plans in accordance with CBC and California Electrical Code requirements for each type of use. Artificial light. Artificial light shall be provided that is adequate to provide an average illumination of 10’candles (107 lux) over the area of the room at a height of 30”above the floor level.
Submit T-24 energy calculations for to show compliance with new store front glazing. This building is subject to the State of California Energy Conservation Regulations:
- The permit applicant shall be responsible for obtaining an energy plan check from a consultant who is
qualified to perform an energy efficiency analysis in accordance with the California Code of Regulations
(CCR,) Title 24, Par 6, 2013 California Energy Code. Glass shall be firmly supported on all four edges. Show on the drawings how compliance shall be made with CBC Section 2404. For glass not firmly supported on all four edges, design shall be submitted to the building official for approval. In lieu of providing structural calculations for justification, show ½” tempered glass with minimum of one clip per joint or 5/8” tempered glass with no clips.Revise door # 115 with 180 degree when door is located in the path of travel and exiting system. Please refer to red marks for additional plan check comments and revise drawings to show compliance.Refer to attached CalGreen and SB 407 and provide completed forms on the drawings.Provide framing around new opening for proposed ATM machine. Clarify if exiting shear wall is modified. Structural calculations may be required for design and justification.