PLAN CHECK NO:
10585430
PROJECT ADDRESS:
215 E Fifteenth St
PLAN CHECK ENGINEER:
Mazarji, ZacTEL:714
647-5831FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/15/2015
105- Repair guards and balcony for 20 Units
INITIAL REVIEW
8/4/2015
EXPIRATION
12/12/2015
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Carlos Losada
3.
TEL:
(562)307-4735
FAX:
VALUATION: $50,000.00
EMAIL:
FLOOD ZONE: X-0602320163J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2013 California Residential Code (CRC); 2013 California Building Code (CBC); CMC = 2013 California Mechanical Code; CPC = 2013 California Plumbing Code; CEC = 2013 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5831 for an appointment.Provide structural calculations and drawings, stamped and signed by a California licensed architect or registered civil engineer for:
- Handrail(s)/guard(s). (Including all connections) CBC Sections 1012, 1013, and 1607.7.
- Guard(s). (Including all connections) CBC Sections 1013 and 1607.7.
Incorporate results of structural calculations into drawings prior to re-submittal.Please refer to red marks on the drawings for additional plan check comments. Revise drawings to show compliance.Show horizontal 1 Hour occupancy separation between existing garage and residence where applicable. Show applicable locations on the drawings.