HomeMy WebLinkAbout214085_2_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10187971
PROJECT ADDRESS:
1900 E Carnegie Ave Unit# A
PLAN CHECK ENGINEER:
Chehade, NabilTEL:714
647-5848FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
F-1, S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
1/19/2016
INITIAL REVIEW
3/4/2016
EXPIRATION
7/17/2016
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Jonathan Iliff
3.
TEL:
(714)632-5027
FAX:
VALUATION:$10,000.00
EMAIL:
jiliff@shelfmaster.com
FLOOD ZONE:X-0602320279J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5848 for an appointment.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Public Works Agency approval (647-5039)Plans are approved and ready for permitting subject to approvals from other depts. as indicated above.