Loading...
HomeMy WebLinkAbout216638_3_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10188836 PROJECT ADDRESS: 3207 S Shannon St PLAN CHECK ENGINEER: Heidari, FredTEL:714 647-5862FAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): B, S-1 PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 4/5/2016 INITIAL REVIEW 4/18/2016 EXPIRATION 10/2/2016 RECHECKS: 1. 06/10/2016 PROJECT APPLICANT CONTACT PERSON: 2. Tim Lux 3. TEL: (949)581-2255 FAX: VALUATION:$698,679.00 EMAIL: datum@pacbell.net FLOOD ZONE:X-0602320258J Therecheck of your project was completed today, 06/10/2016; and item # 6 from the original plan check list need to be completed plus sheet A2.2 where 2nd floor plan and details were shown with the first plan check is not included with this resubmittal. Please bring 3 copies of updated sheet A2.2 to add to these sets, and then obtainthe remaining approvals under item # 6 from the list below. APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Orange County Fire Authority approval on the corrected/final sets of drawings ((714)573-6100) - Police Department approval on the corrected/final set of drawings (647-5840) - Public Works Agency approval (647-5039) - School District Compliance Certificate; a copy of the building permit application, signed by the plan check engineer, shall be required by the School District to verify the scope of work. Refer to the attached handout. - Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide on the drawings a complete door schedule, showing: - Door sizes - Hardware complying with exiting and disabled accessibility requirements - Show compliance with the City of Santa Ana’s Security Ordinance (Contact the Santa Ana Police Department Crime Prevention Section by telephoning 714-647-5840Note on drawing: “Exit doors shall be openable from the inside without the use of a key or any special knowledge or effort.”Regardless of the occupant load, there shall be a floor or landing on each side of a door. The floor or landing shall be not more than ½” lower than the threshold of the doorway. Change in level between ¼” and ½” shall be beveled with a slope no greater than 1:2. Change in level greater than ½” shall be accomplished by means of a ramp. Provide detailed sections and plan views for the new entry door to show compliance.Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. Areas with a vertical clearance of less than 80” under the new stair must have a barrier to warn blind or visually impaired persons.Provide a continuous walking surface from each exit door to public way.Please verify and call out on the site plan that there is no fence on the site to prevent the exits from warehouse and the lunch areas to reach the public way.Revise the drawings to show the words NO PARKING shall be painted on the ground within each loading and unloading access aisle. This notice shall be painted in white letters no less than 12” high and located so that it is visible to traffic enforcement officials. Note on the drawings hot water and drain pipes under lavatory shall be insulated.This building is subject to the State of California Energy Conservation Regulations: - The permit applicant shall be responsible for obtaining an energy plan check from a consultant who is qualified to perform an energy efficiency analysis in accordance with the California Code of Regulations (CCR,) Title 24, Par 6, 2013 California Energy Code. The plan check consultant must sign documentation certifying that a thorough, competent review has been performed on behalf of the Enforcement Agency. - The corrected/final ARCHITECTURAL drawings shall have the required energy efficiency compliance documentation with completed signature blocks filed on the plans. The same information may be copied on the Electrical Plans for the Electrical Plan Checker. - The energy plan check consultant must complete the attached “Energy Conservation Plan Check Consultant Qualification Statement.”See other comments on the following sheets of drawing, sheets:A01, A1.1, A1.2, A2.2and detail 5/AS4. Please resubmit the marked up set with revised plans for recheck.