HomeMy WebLinkAbout216848_4_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 10188891-93-96 PROJECT ADDRESS: 200 W First St Unit# 104, 105, & 106 PLAN CHECK ENGINEER: Heidari, FredTEL:714 647-5862FAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): B PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 4/12/2016 # 14 to be satisfied. INITIAL REVIEW 4/28/2016 EXPIRATION 10/9/2016 RECHECKS: 1. 06/14/2016 PROJECT APPLICANT CONTACT PERSON: 2. 07/20/2016 Nick Servin 3. TEL: (760)533-6532 FAX: VALUATION:$150,000.00 EMAIL: nickservin@gmail.com FLOOD ZONE:X-0602320276J The recheck of your project was completed this morning, 07/20/2016; and your plans are approved subject to item # 14 from the list below. Plans are placed at the public counter for you to pick up and obtain approvals from: Planning, Orange County Fire Authority, Police, Public Works Agency plus the worker’s com. Insurance. The recheck of your project was completed this morning, 06-14-2016; and the following items from the first plan check are not done/ completed at this time. See the list below for items # 3, 9, 10, 11, 12,14 , 25, 27, & 28. APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTS All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.Please return marked up set of drawings with corrections.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2013 California Building Standards Code with local amendments.Please provide a clear plan to show the scope of fire damaged such as: roof area ( entire roof area? or show the limit of damaged area), exterior walls, interior walls, Etc.Please update/ correct the address for this fire damaged building plus the type of construction, and occupancy group. See red marks on sheet A-1 for these items.Plans shall clearly indicate if the restriping parking is to be done under this permit. If it is, please provide construction details to show compliance with Sections 11B-208 and 11B-502 of CBC. Provide completely dimensioned floor plans, elevations and sections of sanitary facility insuring wheelchair clearances complying with CBC Sections 11B-604 &11B-604.8.1.1.2 and the California Plumbing Code.For sheet S-1 & S-2, plan shall clearly show the scope of fire damaged and construction details for rebuild. For roof diaphragm, please call out the plywood nailing and construction details of how the shear will be transferred to shear resisting elements. See other red marks on sheets A-1, A-2, A-3, A-4, A-5, S-1, S-2, S-3, S-4,&T24E.All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Orange County Fire Authority approval on the corrected/final sets of drawings ((714)573-6100) - Police Department approval on the corrected/final set of drawings (647-5840) - Public Works Agency approval (647-5039) - Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide pedestrian protection in accordance with CBC Section 3306. Show location and type of protection on plan view. Provide typical construction details, sections, and elevations of pedestrian protection required. Pedestrian protection constructed within a public right of way shall require a building permit issued by the Building Safety Division and a separate approval from the City’s Public Works Agency (714) 647-5039.Provide the following: - Provide a fully dimensioned site plan on each set of plans. - Disabled access compliance must be shown on the site plan.Provide fire blocking in concealed spaces of stud walls and partitions, including furred spaces at the ceiling and floor level and at 10 ft. intervals both vertical and horizontal.Provide on the drawings a complete door schedule, showing: - Door sizes - Hardware complying with exiting and disabled accessibility - Show compliance with the City of Santa Ana’s Security Ordinance (Contact the Santa Ana Police Department Crime Prevention Section by telephoning 714-647-5840)Note on drawing: “Exit doors shall be openable from the inside without the use of a key or any special knowledge or effort.”All doors require a level floor landing on each side in accordance with CBC. Provide typical door threshold details and details of change in floor covering material.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. CBC required the bottom 10” of all doors except automatic and sliding shall have a smooth uninterrupted surface to allow the door to be opened by a wheelchair footrest without creating a trap or hazardous condition.Tactile exit signs shall be required at the following locations: - Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Chapter 11B: - An accessible entrance - An accessible route to the altered area - Accessible restrooms - Accessible telephone (if any) - Accessible drinking fountains, and - Parking, signage and alarmsIf a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide.Accessible parking spaces serving a particular building shall be located on the shortest accessible route of travel from adjacent parking to an accessible entrance. In parking facilities that do not serve a particular building, accessible parking shall be located on the shortest accessible route of travel to an accessible pedestrian entrance of the parking facility.Sanitary facilities serving the area of new work shall be disabled accessible. Revise the drawings to show compliance with CBC Section11B-604.Note on the drawings hot water and drain pipes under lavatory shall be insulated.Ensure sanitary facilities comply with CBC and that the bottom of the mirror is no higher than 40” from the floor.Glass and glazing shall be in accordance with CBC Chapter 24. Note on the drawings all windows and doors having glazing. Indicate the type and thickness of each light of glazing on the drawings.CBC Section 1603.1.4, Wind design data. The following information related to wind loads shall be shown, regardless of whether wind loads govern the design of the lateral-force-resisting system of the building: - Basic wind speed. - Wind importance factor, I, and occupancy category. - Wind exposure. - The applicable internal pressure coefficient. - The design wind pressures in terms of psf to be used for the design of exterior component and cladding materials not specifically designed by the registered design professional.CBC Section 1603.1.5, Earthquake design data. The following information related to seismic loads shall be shown, regardless of whether seismic loads govern the design of the lateral-force-resisting system of the building: - Seismic importance factor, I, and occupancy category. - Mapped spectral response accelerations, SS and S1. - Site class. - Spectral response coefficients, SDS and SD1. - Seismic design category. - Basic seismic-force-resisting system(s). - Design base shear. - Seismic response coefficient(s), CS. - Response modification factor(s), R. - Analysis procedure used.The engineer or architect in responsible charge of the structural design work shall include in the construction documents the following: - Structural tests and inspections required by CBC Chapter 17. - Inspection and observation program. When special inspection isrequired by Section 1704, the architect or engineer of record shall prepare an inspection program that shall be submitted to the building official for approval prior to issuance of the building permit. - The structural engineer of record shall provide periodic and final inspections for all structural elements to ensure completed construction agrees with his/her design.