HomeMy WebLinkAbout222421_1_Corrections.docxSPC
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10190594
PROJECT ADDRESS:
1325 3/4 S Main St Unit# WCC01
PLAN CHECK ENGINEER:
Chehade, NabilTEL:714
647-5848FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/29/2016
INITIAL REVIEW
9/16/2016
EXPIRATION
2/25/2017
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Virginia Becker
3.
TEL:
(949)930-7458
FAX:
VALUATION:$20,000.00
EMAIL:
virginia.becker@crowncastle.com
FLOOD ZONE:X-0602320276J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5848 for an appointment.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans
should be submitted to expedite the process.
Remove statements from plans for the contractor to verify structural calcs.
Provide detail of the connection of the proposed pipe to the existing pipe at the collar. Show on plans sizes of all pipes and provide calcs to justify adequacy of the pipe and the connections to support the proposed load from the antennas.