HomeMy WebLinkAbout219789_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10189761
PROJECT ADDRESS:
1717 W Sixth St
PLAN CHECK ENGINEER:
So, AnsonTEL:714
647-5830FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
7/21/2016
INITIAL REVIEW
8/30/2016
EXPIRATION
1/17/2017
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Hector Medina
3.
TEL:
(626)912-3987
FAX:
VALUATION: $43,257.00
EMAIL:
hmedina50@inbox.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2013 California Residential Code (CRC); 2013 California Building Code (CBC); CMC = 2013 California Mechanical Code; CPC = 2013 California Plumbing Code; CEC = 2013 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2013 California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.All persons preparing plans for others shall sign those plans. Business and Professions Code Chapter 3, Division 3, Section 5536.1 (a).
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
-Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
Drawings must be to scale and be on 18" x 24" minimum sheets.
Scale of Drawings must be large enough to insure legibility.
Delete notes and details that do not apply to this project.
Delete notes and details that do not apply to this project. (CBC 107)
Specify finish floor elevation of first floor. (CBC 107.2.5)
Prior to the issuance of building permit(s), tract maps, parcel maps, lot line adjustments, public way abandonments, covenant, conditions and restrictions (CC&R's), etc., related to the subject project must be legally recorded with the County of Orange.
TITLE SHEETShow the complete legal description and assessor's parcel number on the plans.The address of the building, and the name and address of the owner(s) and person(s) preparing the plans are required on the first sheet of the plans. (CBC 107)Include address and telephone number of the responsible designer and date of signing of drawings.
Provide building information on plans:
- Occupancy type: R3 / U
- Construction type: Type V – B
- Fire sprinklered: Yes / No
- Fire sprinkler type:(where applicable)Provide complete project description with detailed description of scope of work.
Provide a statement on the title sheet of the plans that this project shall comply with following codes:
- 2013 California Residential Code (CRC)
- 2013 California Building Code (CBC)
- 2013 California Electrical Code (CEC)
- 2013 California Mechanical Code (CMC)
- 2013 California Plumbing Code (CPC)
- 2013 California Green Building Standards Code (CGBS) or CALGreen
- 2013 California Energy Code (CEnC)
- City of Santa Ana Municipal Code
List all deferred submittals on cover sheet. (CRC R106.3.3)
Provide and show on the plans, house street number visible and legible from street. (Minimum 4”High x 1” Wide) CRC R319
Add a note on the cover sheet: “Separate permit(s) is/are required for accessory building, landscape, patio covers, fences, swimming pool, retaining walls, demolition, etc.”
SITE PLAN
Provide building setbacks to finish of exterior walls to all property lines.
Provide eave / overhang / projection setback to all property lines.Projections of dwelling units and accessory buildings without an automatic residential fire sprinkler protection are not permitted less than 2 feet to the property line and are required to be 1 hour fire rated on the underside with a fire separation distance between 2 feet and 5 feet. (CRC Table R302.1 (1))
Lots shall be graded to drain surface water away from foundation walls. The grade shall fall a minimum of 6 inches within the first 10 feet. (CRC R401.3)
FLOORPLANInterior spaces intended for human occupancy shall be provided with heating facilities capable of maintaining a room temperature of 68 degrees Fahrenheit at a point 3 feet above the floor and 2 feet from exterior walls in all habitable rooms. (CRC R303.8)Sheet 1Provide notes for “Security Ordinance” on plan.Sheet 3Revise detail number to “F4” at typical detail on existing foundation on foundation plan.Specify minimum 3 inches side-concrete cover at column base.Detail F3: Specify minimum embedment length for anchor bolt at hold-down.Detail F5: Specify dowel size, spacing and embedment length between existing concrete slab and new concrete slab.Detail F6: Specify material at the one-inch stand-off below the wood post.Provide interior shear-transfer detail at shear-wall between the kitchen and new living room.Sheet 4Section 4B shows ceiling height of 8’-4”. Revise height to 8’-0” to match wall-plates height.