HomeMy WebLinkAbout229990_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10192903
PROJECT ADDRESS:
2 E MacArthur Pl Unit# 300
PLAN CHECK ENGINEER:
Mazarji, ZacTEL:714
647-5831FAX:714
647-5897
TYPE OF CONSTRUCTION:
I A, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
5/8/2017
INITIAL REVIEW
5/18/2017
EXPIRATION
11/4/2017
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Dale Rask
3.
TEL:
(909)390-8392
FAX:
VALUATION:$25,000.00
EMAIL:
drask@trlsystems.com
FLOOD ZONE:X-0602320278JAPPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTSPlease indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5831 for an appointment.This review does not include electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings (949573-6108)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide missing drawings to show compliance with followings incompliance with California Building Code, 2016 CBC:Section 1010.1.9.7 Delayed egress101.1.9.8 Sensor release of electronically locked egress doors10110.1.9.12 Access- controlled elevator lobby doors in high-rise office buildingsIdentify location of type device to be installed on the drawings and provide elevation/s of control device at height of 48” maximum from floor and required accessibility clearance for devise. When applicable, plans shall indicate how required structural and fire resistive integrity will be maintained where a penetration will be made for electrical, and communication conduits, and similar systems. CBC Section 106.1.1 and CBC Chapter 7. Note on the plans the ICC Research Report number, U.L. number, State Fire Marshal number for cloaking of permitted penetrations.