PLAN CHECK NO:
10192530
PROJECT ADDRESS:
1701 3/4 N Main St Unit# WCC01
PLAN CHECK ENGINEER:
Heidari, FredTEL:714
647-5862FAX:714
647-5897
TYPE OF CONSTRUCTION:
III A
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
3/31/2017
INITIAL REVIEW
4/12/2017
EXPIRATION
9/27/2017
RECHECKS:
1. 06/05/2017
PROJECT APPLICANT CONTACT PERSON:
2.
Matthew Vigil
3.
TEL:
(562)889-7925
FAX:
VALUATION:$40,000.00
EMAIL:
FLOOD ZONE:X-0602320163J
The recheck of your plans was completed this morning, 06/05/2017; and plans are approved for building permit issuance subject to item # 3 from the list below. Plans are placed at the plan check counter for your convenience.
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTSResubmit 2corrected sets of plans.This review does not include electrical work. Separate plans, applications, fees, plan checks, and permits is required for electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide structural calculations and drawings, stamped and signed by a California licensed architect or registered civil engineer for:
- New equipment on roof (note on Roof Framing Plan weight of each existing and new piece of equipment on the roof)
- There are two new equipment proposed under this building permit to be placed on the existing roof system, Details 2/A5 and 5/A5. Provide structural calculation and construction details to justify vertical and lateral loads resisting system for this equipment.