HomeMy WebLinkAbout208594_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10186099
PROJECT ADDRESS:
1610 E St Andrew Pl
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
III B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/18/2015
INITIAL REVIEW
9/1/2015
EXPIRATION
2/14/2016
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Jennifer Grob
3.
TEL:
(949)553-0525225
FAX:
VALUATION:$88,000.00
EMAIL:
Jenniferg@dfranzarchitects.com
FLOOD ZONE:X-0602320276J
APPLICABLE CODE: 2013 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.Enlarge path of travel to show compliance with disabled access.CBC Section 1133B.2.5.1, Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.CBC Section 1127B.3, All building entrances that are accessible to and usable by persons with disabilities shall be identified with a least one standard sign and with an additional directional signs, as required, to be visible to persons along approaching pedestrian ways.Exit illumination and exit sign requirements in accordance with CBC Section 1011 shall be shown on the drawings. Be specific as to the type of exit signs to be installed.CBC Section 1011.1. Provide a directional exit sign at changes in exiting direction.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsComplete the attached Disabled Accessibility Documentation Form.Provide a complete suspended ceiling system plan and section detail showing the following:
- Vertical supports
- Seismic wires
- Seismic strut/Compression strut
- Perimeter wires
- Separate fixture wires for lights and mechanical devices
- ICC Research Report number for the suspended ceilingThe reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Provide ICC report for suspended ceilings. Show glazing for door 101 is tempered.Please fillout attached disabled compliance form.