TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
S-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/22/2017
INITIAL REVIEW
12/6/2017
EXPIRATION
5/21/2018
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Duc Nguyen
3.
TEL:
(714)425-1467
FAX:
VALUATION:$50,000.00
EMAIL:
mvicorp@sbcglobal.net
FLOOD ZONE:A-0602320256J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5848 for an appointment.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- School District Compliance Certificate; a copy of the building permit application, signed by the plan check
engineer, shall be required by the School District to verify the scope of work. Refer to the attached handout.
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSpecify the exact use of the building, provide an occupancy classification based on the proposed used as defined in chapter three of the California building code.From the plans provided this building is not an S occupancy.Provide a statement to indicate the type of soil the foundation is placed in based on observation of the design engineer. Clarify if the soil is non-disturbed or compacted. If compacted is there a compaction report?Provide opening calculation to show the building complies with the maximum amount of opening allowed under chapter 7 table 705.8 of the exterior walls.Provide an accessible path of travel from the proposed building to the exiting building.Provide lever type hardware on all doors.Add a note to plans that all doors to be openable from the inside without the use of a key or any special knowledge or effort.Provide a construction section through the clear story that show shows a continuous load path from the upper roof diaphragm to the foundation.Clarify through a section if there is a double plate above the header; otherwise provide starps at the headers to the double plate.Provide a detail of the proposed columns. Are there posts? Or wall framing? Eitherway provide support for the beams.Provide notes and details to show compliance witn the California Green Building Code.