HomeMy WebLinkAbout237893_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10195370
PROJECT ADDRESS:
1971 E Seventeenth St Unit# A
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
III B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
1/24/2018
INITIAL REVIEW
1/28/2018
EXPIRATION
7/23/2018
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Joseph Church
3.
TEL:
(720)946-3228
FAX:
VALUATION:$49,362.00
EMAIL:
church@joearchitect.com
FLOOD ZONE:X-0602320164J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Provide the following:
- Disabled access compliance must be shown on the site plan.Provide typical section view detail of all new partitions and ceilings showing:
- Size, spacing, and material of framing members
- Note gauge and ICC Research Report number and installation/construction requirements for metal framing
members.
- Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13
for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations
and drawing prepared by a registered engineer are submitted for review. Submit structural engineering
calculations for walls in rooms with a floor to building structure above height greater than 14’.
- Provide on the drawings details for the lateral support of partitions, rails and similar space dividers less than
5’ 9” in height.
- Sheathing material and details of attachment. Note type, size, and spacing of fasteners.
- Heights of partition, suspended ceiling, structure above.Show how the wall on section 1/A8.1 supported laterally.Show how glass door and side light are being supported laterally and vertically.Provide thickness of the glazing in the hallway.Complete all soffit and furred out wall details. Provide complete detailing, including number, type, location of fasteners and how attachment is made to the building structure. Show compliance with CBC Section 803.Provide calculation and complete framing plan with detail for gypsum board ceiling .Show size of the new store front door.CBC Sections 1133B.2.4 and 1133B.2.4.1, Regardless of the occupant load, there shall be a floor or landing on each side of a door. The floor or landing shall be not more than ½” lower than the threshold of the doorway. Change in level between ¼” and ½” shall be beveled with a slope no greater than 1:2. Change in level greater than ½” shall be accomplished by means of a ramp. Provide detailed sections and plan views showing compliance at all doorways requiring accessibility.CBC Section 1133B.2.5.1, Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.CBC Section 1133B.2.5, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Provide minimum 36 “ wide accessible counter.Show the bathroom is in compliance with 11B-603.CBC Section 1011.1. Provide a directional exit sign at changes in exiting direction.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of a stairway or ramp shall be
identified by a tactile exit sign with the following words as appropriate:“EXIT STAIR DOWN”“EXIT RAMP DOWN”“EXIT STAIR UP”“EXIT RAMP UP”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsProvide truncated dome at the curb ramp.CBC Sections 1115B and 1210. Sanitation facility toilet room floors shall have a smooth, hard, non-absorbent surface such as Portland cement, concrete, ceramic tile or other approved material which extends upward onto the walls at least 6”. Walls within 2’ of the front and sides of urinals and water closets shall be similarly finished to a height of 4’.CBC Section 1607.7. Provide complete grab bar details on the drawings showing compliance with CBC Section 1115B.8 including structural strength to support a 250 pound point load.CBC Section 1115B.4.3 Item 4. Note on the drawings hot water and drain pipes under lavatory shall be insulated.Complete the attached Disabled Accessibility Documentation Form.This building is subject to the State of California Energy Conservation Regulations:
- The permit applicant shall be responsible for obtaining an energy plan check from a consultant who is
qualified to perform an energy efficiency analysis in accordance with the California Code of Regulations
(CCR,) Title 24, Par 6, 2016 California Energy Code. The plan check consultant must sign documentation
certifying that a thorough, competent review has been performed on behalf of the Enforcement Agency.
- The corrected/final ARCHITECTURAL drawings shall have the required energy efficiency compliance
documentation with completed signature blocks filed on the plans. The same information may be copied on
the Electrical Plans for the Electrical Plan Checker.
- The energy plan check consultant must complete the attached “Energy Conservation Plan Check Consultant
Qualification Statement.”Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636. (Or see comment 29 to 31 )Provide a complete suspended ceiling system plan and section detail showing the following:
- Vertical supports
- Seismic wires
- Seismic strut/Compression strut
- Perimeter wires
- Separate fixture wires for lights and mechanical devices
- ICC Research Report number for the suspended ceilingThe reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)What is the use mechanical rack. What is it supporting, weight of the unit. Provide complete construction detail and support. Please note, calculation might be required.GREEN BUILDING CODEFor first time occupancy provide required items, if it doesn’t apply make a note on the drawings.Provide Bicycle parking per Green Bldg Code 2016 section 5.106.4.Provide Electrical Vehicle (EV ) charging per section 5.106.5.3.Provide information for water conserving plumbing fixture Sec 5.303.3Provide exterior door protection per Sec 5.407.2.2.1Please note all mandatory measures for Green Building Code requirements per standar 2016.Please fillout attached CAL GREEN non-Residential check list on the drawings.Please make a note “ GREEN BUILDING NON RESIDENTIAL Certification check list shall be signed by responsible party and submitted to inspector for final inspection.