HomeMy WebLinkAbout237002_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10195109
PROJECT ADDRESS:
1233 1/2 S Birch St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
12/19/2017
INITIAL REVIEW
1/5/2018
EXPIRATION
6/17/2018
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Chris Salas
3.
TEL:
(818)426-3891
FAX:
VALUATION: $64,201.00
EMAIL:
csalas96@aol.com
FLOOD ZONE: X-0602320276J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2016 California Residential Code (CRC); 2016 California Building Code (CBC); CMC = 2016 California Mechanical Code; CPC = 2016 California Plumbing Code; CEC = 2016 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
All drawings and supporting documents shall be prepared, stamped, and signed by a California licensed architect or registered professional engineer. (CRC R301.1.3, CBC 107.1 and 107.3.4.1).
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Police Department approval on the corrected/final set of drawings (647-5840).
-Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
- School District Compliance Certificate; and a copy of the building permit application, signed by
the plan check engineer, shall be required by the School District to verify the scope of the work.
In addition to other fees, a "Park Acquisition and Development Fee" in the amount shownbelow
shall be required pursuant to a resolution of the City Council for the Recreation andCommunity
Services Agency; net addition of ________ bedroom(s).Amount of $3,206.86; net addition of 1 bedroom
Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper. Show 30-inch clear width for water closet compartments and 24-inch clearance in front of a water closet. Interior spaces intended for human occupancy shall be provided with heating facilities capable of maintaining a room temperature of 68 degrees Fahrenheit at a point 3 feet above the floor and 2 feet from exterior walls in all habitable rooms. (CRC R303.8)Please verify if the roofing material is Tile or comp shingle.Specify ICC approval number and weight per square foot for tile and special roof coverings. (CRC R905.3.4 and R905.3.5) Provide cross ventilation for attic and each enclosed rafter space as specified in CRC Section R806.
The City has encountered a large number of inspection problems arising from a lack of specific framing details. The following listed items are required to be shown on the plans (CBC 107.1):
- All plumbing walls are to be framed with a minimum of 6" studs.
On site plan show how the water will stay away from the structure or provide grading plan.
For plywood roof specify thickness, grade, T&G edges, panel span rating, nailing schedule and required blocking and panel layout pattern.
Provide strap from shear wall to 4x 8 beam.The residence shall conform to the State Energy Conservation Standards. Submit forms and calculations for review and blueprint the final forms on the plans.
- Signed Energy Efficiency Documents must be printed on the plans.
- Also, submit 2 copies of signed Energy Efficiency calculations.
- The corrected/final drawings shall have the required energy efficiency compliance documentation
with completed signature blocks filed on the plans.
-The energy plan check consultant must sign documentation forms on behalf of the Building
Safety Division. Submit a complete energy compliance package complying with 2016 CESC The CF-1R form is to be signed by the Document Author and Building Designer and incorporated into the plans.Revise framing plans to indicate insulation for walls R=, ceiling R= for climate zone 8. Please note on the drawings all mandatory measures for Green building requirements per Green Building code 2016.Please fill out attached CAL GREEN residential check list on the drawings.