HomeMy WebLinkAbout234282_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10194211
PROJECT ADDRESS:
2125 N Main St
PLAN CHECK ENGINEER:
Mazarji, ZacTEL:714
647-5831FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, to be determined (Possible change of occupancy)
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/9/2017
In-complete drawings for Historic house relocation. This permit is not for occupancy.
INITIAL REVIEW
1/3/2018
EXPIRATION
5/8/2018
RECHECKS:
1.5-7-18
PROJECT APPLICANT CONTACT PERSON:
2.
Milford Moralde
3.
TEL:
(714)639-9860326
FAX:
VALUATION:$70,000.00
EMAIL:
milfordm@architectsorange.com
FLOOD ZONE:X-0602320163J
Re-check: 5-7-18
Provide enlarged site plan to show distance from proposed wheelchair lift to property line facing Main Street. The wheelchair and door in open position to remain inside of property line. Obtain planning department to insure location of wheelchair lift meeting planning department requirement.
Please cross Key notes not applicable to this permit. Relocation only and add not to Key note # 2 that future Bar to require building permit and not part of this permit.
Reference Sheet S2.1, detail 17 1nd 18, and Show minimum 18-inch underfloor clearance from grade to bottom of floor joists and minimum 12-inch clearance to bottom of girders.
Correct structural calculation job address to 2125 S. Main Street.
Please List all deferred submittals on cover sheet. Sprinklered system is deferred submittal and contact Permit Technician at Building department for submittal requirement.
Please call plan check engineer at 714-647-5831 for appointment for over counter review once above comments are address on the revised signed and stamped drawings.
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTSMeetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5831 for an appointment, if needed.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2016 California Building Standards Code with local amendments. Submitted drawings showing new foundation only. Complete architectural and structural drawings including accessibility compliance to be submitted based on new use/occupancy. Complete structural calculations are required for new use/occupancy. Additional plan check comments to follow once complete calculations and drawings are submitted for review. In addition to the 2016 California Building Code, this project is subject to the provisions of the 2016California Historical Building Code.Additions, alterations or repairs made to any building constructed prior to January 1, 1946, other than an R-Occupancy building, exceeds $50,000 in cost in any one-year period, then either (A) the entire building must be completely sprinklered in accordance with fire department standards, or (B) the building must comply with requirements as outlined under Santa Ana Municipal Code (SAMC) Section 8-150. A copy of SAMC Section 8-150 may be obtained by visiting the City of Santa Ana’s website at www.santa-ana.org.Additional plan check comments to follow once complete calculations and drawings are submitted for review.