PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10195876
PROJECT ADDRESS:
2121 N Grand Ave
PLAN CHECK ENGINEER:
Chehade, NabilTEL:714
647-5848FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
A-3, E
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
3/19/2018
INITIAL REVIEW
4/5/2018
EXPIRATION
9/15/2018
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Michael Santillan
3.
TEL:
(714)803-8454
FAX:
VALUATION:$50,000.00
EMAIL:
ms@msarchitects.us
FLOOD ZONE:X-0602320163J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2 corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5848 for an appointment.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Public Works Agency approval (647-5039)This project need approval from OCFA ( Fire) .Our record shows that the building is sprinklered. Please add information to plans.Where are the condenser units located on the site plans?It appears that a new opening is being made in the exterior wall of the building.; please provide structural details.Specify on the plans whether or not any of the walls being penetrated is of fire rated constructon.What type of weather protection is provided for the exterior ducts.Sheet S1 and S2 are to be signed design engineer.